Progress report.
Discussion
Dave PORTER said:
You may be better off buying an oversize head stud kit from arp,you will have to slightly drill out the heads, that will prevent any furher problems, as used on the old tuscan RV8.
Will I've allready paid for a standard set, else would have been a good idea.hopfully there not all U/S as I'll just have to repair a few.
Leigh
Barkychoc said:
Leigh - looking good.
I don't know if it will be an issue but in the S the rear gearbox mount is mounted to the chassis via rubber bushes.
If you need any pics let me know.
Chris
I'm still using the standard SD1 rubbers fitted to the rear of the gearbox.I don't know if it will be an issue but in the S the rear gearbox mount is mounted to the chassis via rubber bushes.
If you need any pics let me know.
Chris
so it will have some give.
Small update.
New PAS system is now in and working, well need to sort the PAS bit, but going to re-do most of the wiring.
Made custom brackets for new Rad. and did test install of rad, and then removed.
Test fitted bonnet, and re-fitted bonnet fixings
Fitted 2 fuel pumps, 1 Swirl pot and 1 Filter. and all wiring and plumbing.
Fitted Fuel Lines and Returns
Fitted trigger wheel to crank pullie.
Removed Crank.
Boxed up Crank, Flywheel, Clutch and pully, piston etc ready for balancing.
New PAS system is now in and working, well need to sort the PAS bit, but going to re-do most of the wiring.
Made custom brackets for new Rad. and did test install of rad, and then removed.
Test fitted bonnet, and re-fitted bonnet fixings
Fitted 2 fuel pumps, 1 Swirl pot and 1 Filter. and all wiring and plumbing.
Fitted Fuel Lines and Returns
Fitted trigger wheel to crank pullie.
Removed Crank.
Boxed up Crank, Flywheel, Clutch and pully, piston etc ready for balancing.
It's looking more like a car in progress than a pile of parts.
All the fuel system is in, and working 2 pumps swirl pot and filter, all plumbing and elecrics.
Fitted new rear cooling ducting.
Gear box is in.
PAS column and Digital Dash is now in a powered.
Battery is in need's some brackets tho.
New custom rad Brackets.
All the fuel system is in, and working 2 pumps swirl pot and filter, all plumbing and elecrics.
Fitted new rear cooling ducting.
Gear box is in.
PAS column and Digital Dash is now in a powered.
Battery is in need's some brackets tho.
New custom rad Brackets.
Edited by TVRleigh_BBWR on Tuesday 6th May 12:04