Laying laminate and tiles on newly laid Screed?
Discussion
I believe I know the answer but just wanted to check.....
I am having some screed put down to even out the concrete floors. The extension of the house is approx 3 cm lower.
Approx 45 sq ft of screed will be laid with 3 cm depth
Majority of the screed will be covered with an underlay with laminate laid on top. A small amount will be tiled over.
From my understanding i need to wait 1 day per mm of screed laid... Is this over cautious or can I lay the flooring earlier?
What are peoples experience when they have laid the flooring down soon after the screed has been laid.
Will the type of screed laid also make a diference?
I am having some screed put down to even out the concrete floors. The extension of the house is approx 3 cm lower.
Approx 45 sq ft of screed will be laid with 3 cm depth
Majority of the screed will be covered with an underlay with laminate laid on top. A small amount will be tiled over.
From my understanding i need to wait 1 day per mm of screed laid... Is this over cautious or can I lay the flooring earlier?
What are peoples experience when they have laid the flooring down soon after the screed has been laid.
Will the type of screed laid also make a diference?