Rewire - going rate? with builders in house concurrently?

Rewire - going rate? with builders in house concurrently?

Author
Discussion

Jamp

Original Poster:

200 posts

137 months

Saturday 28th February 2015
quotequote all
Hi All,

I'm trying to sort out a dispute between a family member and an electrician who has rewired their 3 bed terraced house and garage. The electrician was engaged via the builder who is doing a full refurb of the house.

The electrician quoted for the works relating to the kitchen refurb, a new consumer unit, and safety cert for letting the property. On arrival he advised that the house should be fully rewired as it would be cheaper than rectifying the faults in the wiring. Unfortunately a revised quote was not obtained and money wasn't discussed, but he was instructed (via the builder) to proceed with what was necessary. We were expecting a bill perhaps 150% - 200% of the original quote, but the bill is around 600%.

The Consumers' Association suggest rewiring a 3 bed should come in at an average price of £3200+vat, maximum of £4000+vat and 10 man days. We are looking at over double the average and 18 man days. The only complications of this job is that the builders and some furniture were in the house at the time of the rewire, so things needed a bit of moving about (by the builders, but I guess wasting a bit of time for the spark). The builders did do all the chasing out and replastering so that's not factored in. The electrician is arguing that this job was exceptional, but surely a rewire is never straightforward as it's always in an old building, potentially with some of the owners' stuff in the way? I'm trying to judge what is reasonable and get the matter settled, so it would be really helpful if anyone has any guidance on a reasonable time/sum for this sort of work?

Jamp

Original Poster:

200 posts

137 months

Saturday 28th February 2015
quotequote all
Thanks. Yes, lesson learned on getting a quote, believe me!

2 men for 81 hours each, over 9 days, is what he is claiming. It's not a big house though does have a detached garage (though the armoured cable was just tested, not replaced). There weren't many additions, just a few extra sockets, FSUs and hob supply in the kitchen and a couple of security lights on the back and garage, and all of those were in the original scope of work. The rest of the house has just been like for like. There was some 'quirky' wiring in it before but that was just ripped out and replaced.

Apparently he's a NICEIC Domestic Installer. It sounds as though that means he's restricted to certifying his own work as safe but not existing? In which case he couldn't have approved the original install even if it were good, and was always going to have to do a full rewire. Not sure we've understood the NICEIC correctly though, but that's the gist of what they have told my relative.

Jamp

Original Poster:

200 posts

137 months

Saturday 28th February 2015
quotequote all
Nuisance_Value said:
Who is he working for, you or the builder? If it's the builder, then dependent on your contract (you have one with your builder I take it) you will be able to pay him (the builder) a fair and reasonable cost (based on the previous quote) and it'll be up to the electrician to justify his costs to the builder.

If he's working for you, you could argue that you never instructed him to proceed so he should chase the builder for additional costs beyond a fair and reasonable cost of the works completed as it was the builder that instructed him.

Looks to me like he quoted the job, played a bit of a fast one, decided to work it as a time and line job and throw a bill in at the end to make a quick buck.

Has he or the builder got any paperwork to substantiate his time on site?

edit; just read that the builder engaged him. I would be going back to the builder with your findings and telling him to provide some back up as to why it took longer / cost more than is claimed. And remind him that you have no contract with the electrician, it's up to the builder to manage him on site. Builder is passing the buck on this one.

Edited by Nuisance_Value on Saturday 28th February 10:38
I don't think the builder will finish the job if I get him involved. In the contract/scope of work with the builder he was to liaise with the electrician but get the electrician to quote separately. Therefore we don't have a contract with the electrician, but nor with the builder for doing the electrics. It worked fine that way with the plasterer, but we can see now why it's not a good way of managing it. I agree the builder has let us down badly on it but I suspect our contract with him re electrics is too tenuous to hold him legally accountable, and it will cause a whole load more hassle and expense re finishing the works if I tried

The builder says the electrician was indeed on site for the 9 days. The electrician has given copies of invoices that substantiate him being local to site on about 5 days.

Thanks for all responses. That gives me some guidance as to what to offer to settle.