Insufficient fall on sewer

Author
Discussion

Labbetts

Original Poster:

846 posts

140 months

Monday 9th January 2017
quotequote all
Hi chaps

About to start on a big double storey side and rear extension.

We have a manhole close to the rear of the property.

We have a sewer that runs perpendicular from a neighbouring house before joining ours and running to front (currently under kitchen)

We're having to redirect this sewer down the sideway and reconnect it at the front manhole by the street. Builder wants to eliminte/redirect them out of the way.

Anyway, he lifted all the manholes today (he's not actually starting for 8 weeks) and was very surprised by the lack of fall between the rear and front of the property. It's currently only a 10cm fall - over a distance of what must be 60 odd feet.

We used to get problems with blockages, but not for about 10 years or so.

Anyway, question.

If the fall on the drain is too shallow, isn’t it Thames Waters job to sort?

It’s technically a public sewer and it feels like i might have to pay to put right a poor design. With or without our new extension.

Existing manholes have been down for well over 15 years, if not original.
House is circa 1928 - Semi detached.

Labbetts

Original Poster:

846 posts

140 months

Tuesday 10th January 2017
quotequote all
Fastpedeller said:
My understanding is that the ideal fall needs to be 1:40 - apparently the Romans found this to be correct ..... who am I to disagree with them! Much shallower and flow won't work well, much steeper and fluid will flow too quickly and leave solid behind.
This was my undertsanding as well.

Also, that in some circumastances the local authority will allow for a 1:80.

But what if the drain was built with a 1:180, like mine?
Shouldn't be my problem to put right, surely.

Thanks for the swift replies guys.

Labbetts

Original Poster:

846 posts

140 months

Thursday 12th January 2017
quotequote all
guitarcarfanatic said:
I presume you are having to move the sewer as part of the conditions implied by Thames?

What did they say when you made the request to move their asset? Did they mention having to correct fall?

Normally, they will ask for a survey to be completed prior to you building. Off the back of this, they will then outline what needs to happen. If you haven't got their OK, your builder should not be adjusting or touching it - it's their asset and if there are issues with fall, if you adjust the system, they could try and pin on you at a later date.

Of course, if you do involve them, they may try to restrict your plans so I guess that may influence whether you go to them or not.

If the fall is poor and cannot be adjusted, there are ways around it. You may be able to get away with it, but changing the route will obviously lengthen the pipework and reduce the fall further. A pumped chamber could be a solution, or you may be able to chase the pipework back upstream to get a better run.
Thanks for all the great replies chaps.

I haven't engaged said water company yet. So nothing has been mandated yet. The builder wants to re-route the soil pipes down the side access, to simply eliminate them from any future headaches (no doubt a preferable option). There will be a few build overs and around 5m, or thereabouts of additional pipework. It works well at present, despite the shallow fall, so hoping the water company will be ok.

Labbetts

Original Poster:

846 posts

140 months

Thursday 12th January 2017
quotequote all
mk1fan said:
I would revise that last sentence to 'until you know what you are proposing.'

What ever you propose you are going to need to engage with Thames Water. Shared drains are now, by recent statute, the responsibility of the loacal Water Board. Doesn't mean they have always been. Indeed, the Water Board may have had no involvement at all in the construction and routing of the drain.

If you would like to start in 8-weeks then you need to be apply to Thames Water ASAP.
Many thanks for your thorough summation.

Labbetts

Original Poster:

846 posts

140 months

Friday 13th January 2017
quotequote all
AlmostUseful said:
That's near enough corrrect from a Building Regs point of view, but you can only go to 1/150 if the pipe is 150mm dia and not 100mm.

Equally, this is a building regs allowance, and regardless of number of WCs connected some of the more belligerent water authorities would still not accept it unless 10 properties are connected.
I actually made an error.
Fall is 200mm and arhitect is proposing that we upgrade the pipe from 100mm to 150mm PVC - says it gives very little additional resistance.

Labbetts

Original Poster:

846 posts

140 months

Saturday 14th January 2017
quotequote all
AlmostUseful said:
I don't know why, but I had it in my mind from the first time I read the thread that this was your own drain, as it's not it's a slightly different approach.
A 1/90 fall isn't awful, it's certainly not ideal however and unless your replacing/diverting on a like for like basis you'all struggle to get it approved. Upgrading to 150mm may seem an ideal option, but you need to ensure you have a 150mm connection at the lower end to tie in to, you won't get approval for a 150mm pipe to go into a 100mm pipe.

Your 200mm drop is also reduced to 150mm because you drop 50mm at the U/S invert to ensure level soffits which reduces your gradient further to 1/120.

I've done very little with Thames so wouldn't like to comment with too much certainty, but in my patch I submit these things to Suth West Water, Southern Water, Wessex and Severn Trent - Wessex wouldn't think twice about accepting such a proposal, SWW would make me submit far more calcs than are truly required but will eventually accept that their guys know less than me and its just easier if they give up, Southern would take months to respond to my letter because they're too busy so I'd forget about it and give it to one of my grads to sort out and STW would accept it with some careful caveating.

The key here is asset protection, if what you're doing is in anyway damaging to the fabric or performance of their sewer they'll say no. Personally I'd be happy with two or three houses going into a six inch pipe at one in one twenty but I'm not the one approving it!

Also my keyboard is doing strange things on the iPad so apologies for the sudden turn into typing full numbers rather than using digits...
Thanks mate. Spot on response.
In your view, would I be better sticking with a 100m pipe then?
The diversion isn't radical.
It will run parallel to the exitisting pipe (front to back), albeit about 1.5m nearer to the boundary.



Labbetts

Original Poster:

846 posts

140 months

Sunday 15th January 2017
quotequote all
AlmostUseful said:
Does it only serve the two properties?
Touch and go really, bit too slack at 100mm really, but not enough flow to keep a 150 pipe flowing sufficiently.

Building Reg's would allow the 150mm with about 3 WCs in so I'd be happy with it if private.

But SFA6th and 7th are quite specific in what they allo.

If it's only 2 houses Could you guesstimate the amount of toilets, wash hand basins, kitchen sinks, baths, dishwashers and showers in and I'll do the maths on Monday and get back to you.

If it's more houses than 2 just go with the 150mm.
Yep, it just serves the 2 houses.

Ours will go from a one toilet one bathroom arrangement (not changed layout since 1928) to 3 toilets, 2 showers, one bath, 5 sinks (includes kitchen + utility), dishwasher, washing machine.

Neighbours have one downstairs toilet and one bathroom upstairs. So i'd hazard a guess at 3 sinks, 1 shower, 1 bath, 2 toilets. Washing machine and dishwasher.

PS: I could have paid you to do my submission! oh well.

Labbetts

Original Poster:

846 posts

140 months

Sunday 15th January 2017
quotequote all
AlmostUseful said:
Leave it with me, I'll do you something you can submit.
Very very kind sir. I'll check with my architect, but I think he might have already submitted it.
Would be very useful to gauge feedback if things get refused etc. I'm hoping it will all be ok, builder and architect are both confident.

Labbetts

Original Poster:

846 posts

140 months

Monday 23rd January 2017
quotequote all
AlmostUseful said:
OP, if you send me a PM I'll fling you the calcs, I'd go with the pipe at 100mm as a first request to Thames, it's pretty much a like for like diversion so should be acceptable with the flows I've got for you.
hi - i did send you a PM, just double checking to see if you got it.

Labbetts

Original Poster:

846 posts

140 months

Thursday 30th March 2017
quotequote all
AlmostUseful said:
I did not! And then I did...
Turns out that when I got my new phone I only put one of my email addresses into the mail app so don't get notifications from here! Will send you a note tomorrow now I've found it.
getmecoat
Am just resurfacing this thread. Have sent you a PM sir.