Tampolli SR2/LMP675 Full Ground Up Rebuild In Pictures

Tampolli SR2/LMP675 Full Ground Up Rebuild In Pictures

Author
Discussion

BornAgainGT

Original Poster:

69 posts

174 months

Tuesday 21st December 2010
quotequote all
Something for those of you that are interested in the engineering side of open top sports car racing.

Earlier in the year I purchased a Tampolli SR2/LMP675 chassis number #006
The car was campaigned on and off up to and through 2005, where it has stood idle since.

We are currently conducting a full ground up re-build of this car as well as adding in some newer features.
I thought it may be on interest to some of you.

Anyway please enjoy.


BornAgainGT

Original Poster:

69 posts

174 months

Tuesday 21st December 2010
quotequote all

Chassis plate

Full chassis strip down and powder coat

Full chassis strip down and powder coat

New inner floor panels

New outer floor panels

New side protection panels and bag tank

New rear panel

Rebuilt and powder coated front suspension

BornAgainGT

Original Poster:

69 posts

174 months

Tuesday 21st December 2010
quotequote all

Completed front suspension

Custom front engine pick up and inlet manifold

Dry run of engine and bell housing chassis pick up points

Dry run of engine and bell housing chassis pick up points

Transaxle installeld, rebuilt and powder coated rear suspension, exhaust fabrication

Exhaust fabrication and carbon rear under tray fitment

Front bells, discs and wheel speeed sensors (traction control and launch control being fitted)

BornAgainGT

Original Poster:

69 posts

174 months

Thursday 23rd December 2010
quotequote all
From what I am told they did indeed run with ballast, as to what amount I am unsure.
Stupidly we forgot to check the weight of the car before the full strip.
I cannot help but think this is going to come in lighter than 675KG, to what extent I do not know.

I will however update you once we have all four corners on, it will be interesting to see how the weight grows as the project moves forward.

BornAgainGT

Original Poster:

69 posts

174 months

Thursday 23rd December 2010
quotequote all
No planned series as such for this car as yet, although after speaking to Alun at ISL Motorsports early today there is a possibility for the BritCar series. This is something Alun is looking into.

BornAgainGT

Original Poster:

69 posts

174 months

Tuesday 28th December 2010
quotequote all

Brake callipers, lines and reservoirs fitted

Carbon nose and outriggers fitted

Carbon splitter and front under tray fitted incorporates controlled air flow to side mounted radiators while retaining a flat floor

BornAgainGT

Original Poster:

69 posts

174 months

Friday 31st December 2010
quotequote all

Carbon centre and rear floor sections added, radiators and heat exchangers added for plumbing mock up

Centre and rear floor sections from the front

BornAgainGT

Original Poster:

69 posts

174 months

Friday 7th January 2011
quotequote all
Been approved for Britcar! SR2/LMP675 now included in the technical regulations. I received a call from organisers to confirm the same.

BornAgainGT

Original Poster:

69 posts

174 months

Friday 7th January 2011
quotequote all

New custom billet dry sump with revised lower chassis pick up points

New dry sump on engine. Note machined oil ways with in line filters - great engineering

BornAgainGT

Original Poster:

69 posts

174 months

Thursday 13th January 2011
quotequote all

Throttle bodies

Throttle bodies

Rear suspension re-built

More detail

Completed rear suspension

BornAgainGT

Original Poster:

69 posts

174 months

Friday 28th January 2011
quotequote all

Side pods positioned (not final fitted), exhaust headers in place

Wheel speed sensors fitted

Straight thru exhaust for those VERY rare indeed none limited days

Silenced exhaust for all other times

Rear wing and more detail of the exhaust hangers

Rear end coming together now

BornAgainGT

Original Poster:

69 posts

174 months

Saturday 19th February 2011
quotequote all

Splitter end fences added

Air box

Throttle body trumpets

Rolling again

Rolling again

Rolling again

BornAgainGT

Original Poster:

69 posts

174 months

Tuesday 22nd February 2011
quotequote all

Heat protection and drive shafts installed

Heat protection and drive shafts installed

BornAgainGT

Original Poster:

69 posts

174 months

Tuesday 1st March 2011
quotequote all

Completed front end

Completed front end

Air intake base plate preperation

Air intake base plate preperation

Air intake base plate

Close up

BornAgainGT

Original Poster:

69 posts

174 months

Thursday 3rd March 2011
quotequote all

Splitting the back end to finalise the clutch solution

From another angle

BornAgainGT

Original Poster:

69 posts

174 months

Saturday 19th March 2011
quotequote all

Scratch build wiring loom based around DTA electronics.

Laying out the dash controls

Locating the ECU leaving room for the GCU

Newly powder coated rims mounted

Newly powder coated rims mounted

Getting there

Getting there

Getting there

Currently 633KG

BornAgainGT

Original Poster:

69 posts

174 months

Tuesday 12th April 2011
quotequote all

Completed the machining of the top front engine mount

Shown installed

Powder coated rear wing pylons, air box base

Safety wire nuts

BornAgainGT

Original Poster:

69 posts

174 months

Tuesday 12th April 2011
quotequote all

Many , many hours of work preparing the body work to take carbon wrap

Base wrap complete, just coloured highlights to add

BornAgainGT

Original Poster:

69 posts

174 months

Thursday 14th April 2011
quotequote all

Final fit of the side pods and center section around the roll bar hoop

High level view of same, showing relief for the seat belt pickups

And low level from the side

Could not resist fitting front and rear sections - just to see what she looked like - very pleased

And from high level - again very pleased with the overall look

And finally from the side

Best get her finished then, the track is beckoning...

BornAgainGT

Original Poster:

69 posts

174 months

Thursday 25th August 2011
quotequote all
Back again - been a while but good progress

Body shell removed again and final fit of clutch solution

Release bearing

Gear shift mechanism fitted

Transaxle oil cooler fitted

Build up of the induction system

Induction system complete - bar air box base plate

Fuel system complete