Great Central Railway - News and "Stuff"
Discussion
Our latest wagon overhaul is turning out to be quite extensive...

The floor, although mostly sound, was badly dented and water pools had corroded some holes, the fixed end was also very poorly repaired after heavy damage in Pre GCR time, possibly by being "shunted" by a JCB bucket! The Interior chassis girders have bends in them and a axlebox "W" iron has a fracture as well.
The floor, although mostly sound, was badly dented and water pools had corroded some holes, the fixed end was also very poorly repaired after heavy damage in Pre GCR time, possibly by being "shunted" by a JCB bucket! The Interior chassis girders have bends in them and a axlebox "W" iron has a fracture as well.
I have been away for a couple of weeks but the team has been working hard, so B589204 is now in undercoat but was outside in the rain, so is still awaiting top coat. B570676 is in the shed and has had repairs done to a couple of lower inner stanchions, the East side has been wire brushed down to bare metal and a start has been made on removing the rivets on the "W" iron. Part of the underframe has been prepped and undersealed.
We also have our next wagon brought from Swithland, B573403 which came from Transrail Leamington in 1995. It had a quick clean and paint in 1996 and now needs a floor and some side repairs.



We also have our next wagon brought from Swithland, B573403 which came from Transrail Leamington in 1995. It had a quick clean and paint in 1996 and now needs a floor and some side repairs.



meb90 said:
I don't think I have commented before, but I enjoy reading the updates when you post them and appreciate the amount of work going into the wagons!
How many minerals have you now got for the 'Windcutters' - it must be getting onto be a few now?
Hi mebHow many minerals have you now got for the 'Windcutters' - it must be getting onto be a few now?
We had 39 wagons at one point but 3 went to MOSI (Manchester Museum of Science and Industry). They have now gone to Weardale, Middleton and Blaenavon. Another six are on long term Loan to Blaenavon. So we now have 30. That is enough for two regular freight trains and can make a "Lengthy train".
Of these 22 have been overhauled and repainted in the past five years, we have four at Rothley now, with 2 completed, so there are six to go. We hope to get all running and two/three overhauls/repaints a year. This is all done by volunteers.
Flying Phil said:
Hi meb
We had 39 wagons at one point but 3 went to MOSI (Manchester Museum of Science and Industry). They have now gone to Weardale, Middleton and Blaenavon. Another six are on long term Loan to Blaenavon. So we now have 30. That is enough for two regular freight trains and can make a "Lengthy train".
Of these 22 have been overhauled and repainted in the past five years, we have four at Rothley now, with 2 completed, so there are six to go. We hope to get all running and two/three overhauls/repaints a year. This is all done by volunteers.
That's more than I was expecting you to say, but as you say it means you can put a proper train together.We had 39 wagons at one point but 3 went to MOSI (Manchester Museum of Science and Industry). They have now gone to Weardale, Middleton and Blaenavon. Another six are on long term Loan to Blaenavon. So we now have 30. That is enough for two regular freight trains and can make a "Lengthy train".
Of these 22 have been overhauled and repainted in the past five years, we have four at Rothley now, with 2 completed, so there are six to go. We hope to get all running and two/three overhauls/repaints a year. This is all done by volunteers.
I admire the work you and the other volunteers do - please keep it up
One day I would like to join you, but I can only spin so many plates!Matt
As many will know, we have had some hot weather recently...last week the team had a paintathon on wagon B589204 and painted the grey top coat. I went along yesterday and the paint was still soft and there were some "sags" on the West side which gets the sun all afternoon!


So when it is cooler and the paint is hard we will rub down and re paint before stripes and black box numbering.

Meanwhile in the shed I was able to put some undercoat on #676.


So when it is cooler and the paint is hard we will rub down and re paint before stripes and black box numbering.

Meanwhile in the shed I was able to put some undercoat on #676.
Another first for the Windcutters!
This wagon went up to Leeds to have its wheel tyres "turned" to a correct profile. When it was unloaded I was told that it was actually shunted briefly onto NR rails so the first time a 16Ton Mineral wagon has been on the network in about 30 years! Also the first wagon to have its tyres turned in many years. Thanks to Rothley C&W for shunting and arranging this and the DCRT for funding this work and transport.
[url]
|https://forums-images.pistonheads.com/312401/202607074493293[/url]
Sorry about the picture which needs clicking on to open....I don't know why it is like that? Now sorted.
This wagon went up to Leeds to have its wheel tyres "turned" to a correct profile. When it was unloaded I was told that it was actually shunted briefly onto NR rails so the first time a 16Ton Mineral wagon has been on the network in about 30 years! Also the first wagon to have its tyres turned in many years. Thanks to Rothley C&W for shunting and arranging this and the DCRT for funding this work and transport.
Edited by Flying Phil on Tuesday 7th July 12:29
Sorry about the picture which needs clicking on to open....I don't know why it is like that? Now sorted.
Edited by Flying Phil on Wednesday 15th July 15:17
Edited by Flying Phil on Thursday 15th October 15:48
In other GCR news
The shareholders of Boscastle Locomotive Ltd received excellent news recently that there has been a full and final settlement of the insurance claim following the theft of parts three years ago. It is said that this will cover about 90% of the total cost of the 90 plus stolen parts (None were recovered). This claim has taken a huge amount of time to process and we are very grateful to the GCR and their Insurance Company for their support.
Our fundraising continues for the boiler completion and final assembly costs....but Boscastle's return to steam is getting closer!
A gratuitous picture of the locomotive when it was running in the 1990's

The shareholders of Boscastle Locomotive Ltd received excellent news recently that there has been a full and final settlement of the insurance claim following the theft of parts three years ago. It is said that this will cover about 90% of the total cost of the 90 plus stolen parts (None were recovered). This claim has taken a huge amount of time to process and we are very grateful to the GCR and their Insurance Company for their support.
Our fundraising continues for the boiler completion and final assembly costs....but Boscastle's return to steam is getting closer!
A gratuitous picture of the locomotive when it was running in the 1990's
Other news from the GCR is that the "Factory Flyover" section has gone out to tender with possible contractors. This is the two section viaduct over the Precis Spark car park and bridge over the Railway Terrace road (To the tip site). They hope that the build can start at Christmas and take about a year.
In Windcutter news, we now have our new fixed end made and it is due to be lifted into place when we can have the wagon under the large "A" frame in the yard. We also have the new "W" iron, which the Rothley C & W team will have drilled and rivetted onto B560676.


In Windcutter news, we now have our new fixed end made and it is due to be lifted into place when we can have the wagon under the large "A" frame in the yard. We also have the new "W" iron, which the Rothley C & W team will have drilled and rivetted onto B560676.
On another website, the question was asked about how much does a Windcutter wagon cost to overhaul. So I put together a rough costing by saying a new floor uses about £700 for new steel sheet. But there is also about 40 cutting discs and 80 welding rods. Coating the inside uses about 5l of bitumastic. Painting the outside uses about 2 to 5l of primer, 4l of undercoat and 4l of topcoat. There are also sundries of vac cylinder overhaul, hoses, grinding discs, wire brushes, paint brushes etc....so a broad total cost of about £2500 direct cost.....and about 300 hours of volunteer time (4 people 6 hours per week, three months per overhaul).
We have 30 wagons in the fleet and 23 have been recently (within 6 years) overhauled. There are three now at Rothley for completion over the next 5 months and the last four at Swithland for completion in 2027.
As we hope these overhauls will last about 30 years, with two paint jobs in that time, the future costs will be less.
Seeing Two Windcutter rakes running over this Gala weekend is why we do the work! We are having a Sales stand at Rothley on Sat and Sunday so please come along to speak to the team and show your support.
We have 30 wagons in the fleet and 23 have been recently (within 6 years) overhauled. There are three now at Rothley for completion over the next 5 months and the last four at Swithland for completion in 2027.
As we hope these overhauls will last about 30 years, with two paint jobs in that time, the future costs will be less.
Seeing Two Windcutter rakes running over this Gala weekend is why we do the work! We are having a Sales stand at Rothley on Sat and Sunday so please come along to speak to the team and show your support.