World's largest offshore windfarm starts generating
Discussion
mikey_b said:
Hill92 said:
Dogger Bank A requesting a 4 month extension to transmission licence exemption due to the continuing effects of the 2024 blade failures and associated investigation/ remediation delays.
https://www.gov.uk/government/publications/electri...
For non-windfarm experts, what does that mean in practical terms? Are they sticking meaningful quantities of power into the grid, or are they pushing back 4 months? Or is this something else entirely?https://www.gov.uk/government/publications/electri...
The wind farm is made up of 6 balancing mechanism units of about 200 MW each. The 95 turbines are arranged in 15 strings of turbines around the central Offshore Substation Platform, which is then connected to shore by the HVDC interconnector (the transmission system referred to in the consultation). It could be that they can't operate all the strings at the moment due to ongoing work on some of their turbines.
mikey_b said:
Hill92 said:
Dogger Bank A requesting a 4 month extension to transmission licence exemption due to the continuing effects of the 2024 blade failures and associated investigation/ remediation delays.
https://www.gov.uk/government/publications/electri...
For non-windfarm experts, what does that mean in practical terms? Are they sticking meaningful quantities of power into the grid, or are they pushing back 4 months? Or is this something else entirely?https://www.gov.uk/government/publications/electri...

It is fairly well known the launch of the GE turbine was not good. The build of DBA was slooooooow. There is still lots of rectification works ongoing to get the units online.
We know of a few blades, and Robin Hawkes has been hawkish in spotting jack ups on site there where they shouldnt be etc.
I believe a couple of Turbines will need replacing in entirety.
this is teething problems like never seen before - due almost entirely to GE plant / design / people.
Its a delay to the programme, so much so DBB will be finished / fit before DBA
PushedDover said:

It is fairly well known the launch of the GE turbine was not good. The build of DBA was slooooooow. There is still lots of rectification works ongoing to get the units online.
We know of a few blades, and Robin Hawkes has been hawkish in spotting jack ups on site there where they shouldnt be etc.
I believe a couple of Turbines will need replacing in entirety.
this is teething problems like never seen before - due almost entirely to GE plant / design / people.
Its a delay to the programme, so much so DBB will be finished / fit before DBA
k up" 
dickymint said:
Well we know you're not a GE fan so why the rolleyes at me? Was it not "another f
k up" 
Not many if any GE fans out there, so not as if exclusive to my views.
k up" 
Eye-rolls were for a predicatable non contribution mockery that added nothing to the question from Mikey_b. looking for answers. It was not "another f
kup" no. Sorry if sensitive.Anyone know where the thread that was / or similar to 'The Future of Power Generation in Great Britain' has gone?
I was going to ask what the 'peoples views' were of this currently (less hand wringing, more reality)- but seems moderators have wiped it?
https://www.pistonheads.com/gassing/topic.asp?h=0&...
I was going to ask what the 'peoples views' were of this currently (less hand wringing, more reality)- but seems moderators have wiped it?
https://www.pistonheads.com/gassing/topic.asp?h=0&...
PushedDover said:
Anyone know where the thread that was / or similar to 'The Future of Power Generation in Great Britain' has gone?
I was going to ask what the 'peoples views' were of this currently (less hand wringing, more reality)- but seems moderators have wiped it?
https://www.pistonheads.com/gassing/topic.asp?h=0&...
Here: https://www.pistonheads.com/gassing/topic.asp?h=0&...I was going to ask what the 'peoples views' were of this currently (less hand wringing, more reality)- but seems moderators have wiped it?
https://www.pistonheads.com/gassing/topic.asp?h=0&...
Hill92 said:
PushedDover said:
Anyone know where the thread that was / or similar to 'The Future of Power Generation in Great Britain' has gone?
I was going to ask what the 'peoples views' were of this currently (less hand wringing, more reality)- but seems moderators have wiped it?
https://www.pistonheads.com/gassing/topic.asp?h=0&...
Here: https://www.pistonheads.com/gassing/topic.asp?h=0&...I was going to ask what the 'peoples views' were of this currently (less hand wringing, more reality)- but seems moderators have wiped it?
https://www.pistonheads.com/gassing/topic.asp?h=0&...
PH Search doing a sterling job as always for me

8 month extension granted for DBA. More details on what's happening:
Blades and some nacelle components are being replaced on just over ten turbines at the 95-unit project, it is understood. Towers, nacelles and blades on the two machines affected by blade failures are also due to be replaced.
https://www.renews.biz/offshore-wind/turbine-repai...
Blades and some nacelle components are being replaced on just over ten turbines at the 95-unit project, it is understood. Towers, nacelles and blades on the two machines affected by blade failures are also due to be replaced.
https://www.renews.biz/offshore-wind/turbine-repai...
plfrench said:
Doggerbank A and B are both showing zero output on Robin Hawkes - has something tripped?!
They were doing well over 1GW between them most of yesterday, but today, nothing!
seems back to business today at c.500MW per site.They were doing well over 1GW between them most of yesterday, but today, nothing!
I note Robin Hawkes doesnt cover the Teesside windfarm for some reason
https://renewables-map.robinhawkes.com/#7.72/54.97...
PushedDover said:
plfrench said:
Doggerbank A and B are both showing zero output on Robin Hawkes - has something tripped?!
They were doing well over 1GW between them most of yesterday, but today, nothing!
seems back to business today at c.500MW per site.They were doing well over 1GW between them most of yesterday, but today, nothing!
I note Robin Hawkes doesnt cover the Teesside windfarm for some reason
https://renewables-map.robinhawkes.com/#7.72/54.97...
Same reason why when you switch to the solar view there are lots of solar farms marked with dots but only a handful like Larks Green have generation data.
https://www.nationalgrid.com/uks-first-transmissio...
Distribution-connected generation is also called embedded generation and is normally captured as a reduction in demand on the national transmission system. Some sites adjust for embedded generation using e.g. solar estimates from Sheffield Solar. This is why there are significant differences in reported generation between older grid sites like Grid Templar vs iamkate, Drax Electric Insights, Robin Hawkes etc.