Posting under an anonymous profile because I can be identified from my regular one... Apologies for breaking the rules in this respect.
I'm self-employed in the IT services industry. A small, professional new client engaged my services a few months ago. The deadline for delivery of the work I'm doing was recently set for the end of August. Everything was going well with good communication until a few days ago when after a week of no communication and with no warning the client announced they were subjectively unhappy with a technical aspect of the project and have put the project on hold. I've a feeling I've lost the project since they tell me they're now talking with an alternative supplier. They haven't given me the opportunity to discuss their concerns and find a solution.
Something doesn't seem right. Perhaps they're in financial dire straits or some other problem has arisen. I don't know. They don't seem interested in communicating further with me and their lack of professionalism in this latest development appears to be out of character.
Nevertheless I've spent significant time over the last few weeks working on this project and they know this. However, until it's finished the work I've done so far is virtually worthless to anybody.
We have no written contract in place and haven't discussed or agreed terms other than the price of the whole job, which is a few thousand pounds.
Are any legal bods reading this who would be prepared to answer some quick questions away from this forum that might help me clarify my position please? I'm guessing that I can't invoice for the value of the work completed to date since their announcement is based on a subjective opinion of an aspect of the work they've seen so far with which I can't argue, but am I legally entitled to invoice them for the portion of the work that I've completed, even though they're claiming they don't want it any more?
I'm prepared to pay for legal advice to recover what I can justifiably claim provided the cost of the advice is realistic given what I might receive from my client. At the moment I don't know what that advice might cost nor what I might expect to recover.
Cheers,
M
I'm self-employed in the IT services industry. A small, professional new client engaged my services a few months ago. The deadline for delivery of the work I'm doing was recently set for the end of August. Everything was going well with good communication until a few days ago when after a week of no communication and with no warning the client announced they were subjectively unhappy with a technical aspect of the project and have put the project on hold. I've a feeling I've lost the project since they tell me they're now talking with an alternative supplier. They haven't given me the opportunity to discuss their concerns and find a solution.
Something doesn't seem right. Perhaps they're in financial dire straits or some other problem has arisen. I don't know. They don't seem interested in communicating further with me and their lack of professionalism in this latest development appears to be out of character.
Nevertheless I've spent significant time over the last few weeks working on this project and they know this. However, until it's finished the work I've done so far is virtually worthless to anybody.
We have no written contract in place and haven't discussed or agreed terms other than the price of the whole job, which is a few thousand pounds.
Are any legal bods reading this who would be prepared to answer some quick questions away from this forum that might help me clarify my position please? I'm guessing that I can't invoice for the value of the work completed to date since their announcement is based on a subjective opinion of an aspect of the work they've seen so far with which I can't argue, but am I legally entitled to invoice them for the portion of the work that I've completed, even though they're claiming they don't want it any more?
I'm prepared to pay for legal advice to recover what I can justifiably claim provided the cost of the advice is realistic given what I might receive from my client. At the moment I don't know what that advice might cost nor what I might expect to recover.
Cheers,
M
Thank you all.
Given a manageable risk/reward ratio of course I'm prepared to pay for legal advice.
At this stage I'm seeking advice on whether there are grounds for initating legal proceedings if my client terminates the contract. Solicitors must surely be prepared to discuss the merits of a potential case before being formally engaged to provide legal advice. (Note: At this stage I'm not asking for advice about what to do.)
If I have an idea of whether I would have justifiable grounds to issue an invoice and back it up with action if it goes unpaid, I'll be able to negotiate more effectively with my client should the worst happen.
In the decade that I have been successfully providing these services to many clients I have never experienced this before so I have never needed the legal backup of formal contracts, part-payments and so on. Perhaps this is my lesson-learning project but I would never have guessed that this particular client would be the one to cause me problems.
Cheers,
M
Given a manageable risk/reward ratio of course I'm prepared to pay for legal advice.
At this stage I'm seeking advice on whether there are grounds for initating legal proceedings if my client terminates the contract. Solicitors must surely be prepared to discuss the merits of a potential case before being formally engaged to provide legal advice. (Note: At this stage I'm not asking for advice about what to do.)
If I have an idea of whether I would have justifiable grounds to issue an invoice and back it up with action if it goes unpaid, I'll be able to negotiate more effectively with my client should the worst happen.
In the decade that I have been successfully providing these services to many clients I have never experienced this before so I have never needed the legal backup of formal contracts, part-payments and so on. Perhaps this is my lesson-learning project but I would never have guessed that this particular client would be the one to cause me problems.
Cheers,
M
Being in the industry, sounds like they have had some alternative advice [not necessarily correct] as to the solution to
their problem and decided to bail out. Whenever you go into a company with a view to getting some business, you always
determine that their existing [hardware/software/solution] is not up to scratch - even if still work in progress....
That's one of the problems with IT - so many different possible solutions to the same problem..
[edit]
advice usually comes from the bosses son who once read a something about it .....
[/edit]
their problem and decided to bail out. Whenever you go into a company with a view to getting some business, you always
determine that their existing [hardware/software/solution] is not up to scratch - even if still work in progress....
That's one of the problems with IT - so many different possible solutions to the same problem..
[edit]
advice usually comes from the bosses son who once read a something about it .....
[/edit]
Edited by barney123 on Wednesday 27th August 16:28
Probably not much help to you now, but I would in your position consider joining the Federation of Small Businesses. The free legal cover you get with membership would no doubt get you out of this hole.
I'm not sure if the benefit applies to an ongoing situation when you join, but may be worth asking just in case.
http://www.fsb.org.uk/
Best of luck!
I'm not sure if the benefit applies to an ongoing situation when you join, but may be worth asking just in case.
http://www.fsb.org.uk/
Best of luck!
I'm not a solicitor, but am self employed in a similar field.
FWIW, I'd speak to them, outline the position that their decision has left you in. Explain the fact that they have engaged you in x hours of work and see if you are able to come to some form of amicable agreement, even if it doesn't recompense you to the value you're hoping for.
If they're unwilling to pay anything, then and only then is it time to think about proceedings. Nothing's more sure to alienate someone from you than premature talk of legal action.
Send 'em a bill and a short covering letter inviting them to respond with reason(s) why they think it shouldn't be paid. Their response can be used later as evidence (provided it isn't marked "without prejudice").
Personally I wouldn't involve a solicitor as there's little need. A few grands worth of disagreement can be dealt with in the small claims fast track which'll go to arbitration anyway and'll cost you about 120 quid.
Bottom line is, be nice until it's time not to be.
P.S. Don;t send "without prejudice" letters yourself. It's generally not a clever thing to do.
Hope that helps and good luck fella!!
FWIW, I'd speak to them, outline the position that their decision has left you in. Explain the fact that they have engaged you in x hours of work and see if you are able to come to some form of amicable agreement, even if it doesn't recompense you to the value you're hoping for.
If they're unwilling to pay anything, then and only then is it time to think about proceedings. Nothing's more sure to alienate someone from you than premature talk of legal action.
Send 'em a bill and a short covering letter inviting them to respond with reason(s) why they think it shouldn't be paid. Their response can be used later as evidence (provided it isn't marked "without prejudice").
Personally I wouldn't involve a solicitor as there's little need. A few grands worth of disagreement can be dealt with in the small claims fast track which'll go to arbitration anyway and'll cost you about 120 quid.
Bottom line is, be nice until it's time not to be.
P.S. Don;t send "without prejudice" letters yourself. It's generally not a clever thing to do.
Hope that helps and good luck fella!!
I'd advise them of your position - you have been engaged to undertake work which was specific to them. You have spent X amount of time on the work and thus far your bill is X (stating politely that of course they appreciate that you have provided the services and thus remuneration will be due for the value of the work undertaken to date).
If they wish to proceed, your estimate of the cost to completion is X and you would like payment to be made on account before any future work starts.
You are entitled to bill for work done. This is especially the case when it is a unique bit of work i.e. you cannot sell what you have done onto someone else.
If they wish to proceed, your estimate of the cost to completion is X and you would like payment to be made on account before any future work starts.
You are entitled to bill for work done. This is especially the case when it is a unique bit of work i.e. you cannot sell what you have done onto someone else.
dangerousB said:
Personally I wouldn't involve a solicitor as there's little need. A few grands worth of disagreement can be dealt with in the small claims fast track which'll go to arbitration anyway and'll cost you about 120 quid.
Bottom line is, be nice until it's time not to be.
This seems like good advice to me. They seem to be sympathetic to the small David, rather the larger Goliath. If you have e-mails and your deliverables to date, then you have the basis of a favourable judgement. http://www.hmcourts-service.gov.uk/infoabout/claim...Bottom line is, be nice until it's time not to be.
For the future, I think that you should send your clients a letter of appointment stating your payment terms and conditions which need not be very complicated. Just confirm the agreed objectives, the expected delivery period, hourly charge-out rate and payment period 7, 30 days etc. Make sure your invoice is always below the small claims court max of £5,000.
rdjohn said:
dangerousB said:
Personally I wouldn't involve a solicitor as there's little need. A few grands worth of disagreement can be dealt with in the small claims fast track which'll go to arbitration anyway and'll cost you about 120 quid.
Bottom line is, be nice until it's time not to be.
This seems like good advice to me. They seem to be sympathetic to the small David, rather the larger Goliath. If you have e-mails and your deliverables to date, then you have the basis of a favourable judgement. http://www.hmcourts-service.gov.uk/infoabout/claim...Bottom line is, be nice until it's time not to be.
For the future, I think that you should send your clients a letter of appointment stating your payment terms and conditions which need not be very complicated. Just confirm the agreed objectives, the expected delivery period, hourly charge-out rate and payment period 7, 30 days etc. Make sure your invoice is always below the small claims court max of £5,000.
Money Claim Online now handles claims up to £99,999.99!
The cost doubles though at £5k from about £100 to £200 though. I would say that unless the amount is literally a few quid over the £5k to claim the proper amount.
7db said:
Sometimes you eat the bar, and sometimes, well the bar she eats you.
Do you really want to sue clients? Where is your next job coming from?
With respect, it would appear that the OP isn't likely to get involved with this "client" in the forseeable future.Do you really want to sue clients? Where is your next job coming from?
I would suggest that his next job would come from another "client" and entering into a small claims tribunal with his previous one wouldn't endanger future relationships with other parties.
What was your point? He might lose a claim? Thank you Sherlock

Before engaging in legal proceedings, you want to write at least two letters on the lines as I have suggested - i.e. you owe me this much for services rendered, please pay up by X date. Once X date has passed, another chaser stating if a reply hasn't been received by X Date you will have no alternative but to issue proceedings. Send both these letters by recorded delivery.
This way the court can see you tried to avoid litigation, otherwise they may not be too favourable in terms of determining the value of your work done (i.e. you will get punished for not giving the other side a chance or two to pay up).
This way the court can see you tried to avoid litigation, otherwise they may not be too favourable in terms of determining the value of your work done (i.e. you will get punished for not giving the other side a chance or two to pay up).
Thank you all very much indeed. All of you. There is some excellent advice in those posts and I truly appreciate your input. You have almost restored my faith in Pistonheads. 
Since I wasn't sure how much additional advice the forums would provide before the thread degenerated into the usual melée I called a solicitor specialising in commercial contracts yesterday afternoon who was also very helpful. She advised that I don't have much chance of success making a legal claim to recover payment for the part-completed work because my arrangement with this client isn't formalised in a written contract. So if the contract collapses I intend to try the amicable approach that many of you have suggested, to see whether I can appeal to my client's better nature and recover something. If that fails then I'll chalk this up to experience and move on: I've got plenty of other work to do.
Cheers,
M

Since I wasn't sure how much additional advice the forums would provide before the thread degenerated into the usual melée I called a solicitor specialising in commercial contracts yesterday afternoon who was also very helpful. She advised that I don't have much chance of success making a legal claim to recover payment for the part-completed work because my arrangement with this client isn't formalised in a written contract. So if the contract collapses I intend to try the amicable approach that many of you have suggested, to see whether I can appeal to my client's better nature and recover something. If that fails then I'll chalk this up to experience and move on: I've got plenty of other work to do.
Cheers,
M
Edited by Monday on Thursday 28th August 10:06
I must say I am quite surprised at what the solicitor has said.
I agree though the amicable way forward - stating the fact that you have completed considerable work for the project and that you will be politely asking for payment anyway may cause them to rethink their position in completion.
If that breaks down, I would still consider taking things further. You have a reasonable and legal claim for the work you have done. I am surprised the solicitor has said that.
IMHO the lack of a formalised contract in this situation actually works against them. What is undeniable is that you had a contract in place to complete work and that you have worked towards that. Without a written contract it is very difficult for them (or impossible) to point towards any kind of breach which would justify their pulling out of the contract.
Filling out the court papers takes 20 minutes online. It will cost you £100 which is added to their bill anyway. The official figures of cases where summons is delivered is that something like 97% never get to court as the defendant then knows the situation is serious and prefers to stop bluffing and pay up.
That said, I see no reason why the company would not be reasonable anyway. Failing that, the warning that you are willing to take action is another step which often works, and finally the summons has a huge success rate.
IMHO a client who doesn't pay for work completed is not a client. Chase up your money.
I agree though the amicable way forward - stating the fact that you have completed considerable work for the project and that you will be politely asking for payment anyway may cause them to rethink their position in completion.
If that breaks down, I would still consider taking things further. You have a reasonable and legal claim for the work you have done. I am surprised the solicitor has said that.
IMHO the lack of a formalised contract in this situation actually works against them. What is undeniable is that you had a contract in place to complete work and that you have worked towards that. Without a written contract it is very difficult for them (or impossible) to point towards any kind of breach which would justify their pulling out of the contract.
Filling out the court papers takes 20 minutes online. It will cost you £100 which is added to their bill anyway. The official figures of cases where summons is delivered is that something like 97% never get to court as the defendant then knows the situation is serious and prefers to stop bluffing and pay up.
That said, I see no reason why the company would not be reasonable anyway. Failing that, the warning that you are willing to take action is another step which often works, and finally the summons has a huge success rate.
IMHO a client who doesn't pay for work completed is not a client. Chase up your money.
Monday said:
Thank you all very much indeed. All of you. There is some excellent advice in those posts and I truly appreciate your input. You have almost restored my faith in Pistonheads. 
Since I wasn't sure how much additional advice the forums would provide before the thread degenerated into the usual melée I called a solicitor specialising in commercial contracts yesterday afternoon who was also very helpful. She advised that I don't have much chance of success making a legal claim to recover payment for the part-completed work because my arrangement with this client isn't formalised in a written contract. So if the contract collapses I intend to try the amicable approach that many of you have suggested, to see whether I can appeal to my client's better nature and recover something. If that fails then I'll chalk this up to experience and move on: I've got plenty of other work to do.
Cheers,
M
She's obviously not much good if she missed the main point in your favour here.....
Since I wasn't sure how much additional advice the forums would provide before the thread degenerated into the usual melée I called a solicitor specialising in commercial contracts yesterday afternoon who was also very helpful. She advised that I don't have much chance of success making a legal claim to recover payment for the part-completed work because my arrangement with this client isn't formalised in a written contract. So if the contract collapses I intend to try the amicable approach that many of you have suggested, to see whether I can appeal to my client's better nature and recover something. If that fails then I'll chalk this up to experience and move on: I've got plenty of other work to do.
Cheers,
M
Edited by Monday on Thursday 28th August 10:06
Which is this. You don't have a written contract in place therefore..........
YOU OWN ALL OF THE INTELLECTUAL PROERTY IN THE WORK YOU HAVE DONE. THEY CANNOT USE IT WITHOUT YOUR CONSENT.If they want to use what you've done, they'll have to buy it from you, or start again from scratch.
I am also surprised that the Solicitor told you that lack of contract stuffs you. It makes it more difficult for them to prove you haven't delivered to specification!!
Talk to them. Tell them you want paying for what you've done, plus a bit on top, and you'll sign over the IP in the work done so far.
Edited by Vesuvius 996 on Thursday 28th August 11:55
Vesuvius 996 said:
YOU OWN ALL OF THE INTELLECTUAL PROERTY IN THE WORK YOU HAVE DONE. THEY CANNOT USE IT WITHOUT YOUR CONSENT.If they want to use what you've done, they'll have to buy it from you, or start again from scratch.
@JustinP1:
You make some (more) very interesting points here about the courts' attitude towards little-guy-vs-big-guy situations. Assuming my client formally terminates the contract and I've nothing to lose then formal evidence of my decision to seek compensation could provoke a gesture.
Thank you both for your contribution.
Monday said:
@JustinP1:
You make some (more) very interesting points here about the courts' attitude towards little-guy-vs-big-guy situations. Assuming my client formally terminates the contract and I've nothing to lose then formal evidence of my decision to seek compensation could provoke a gesture.
Thank you both for your contribution.
Its not so much as 'big guy vs little guy' but what has actually occurred, how this relates to the law of the land, and what anyone is prepared to do about it.You make some (more) very interesting points here about the courts' attitude towards little-guy-vs-big-guy situations. Assuming my client formally terminates the contract and I've nothing to lose then formal evidence of my decision to seek compensation could provoke a gesture.
Thank you both for your contribution.
That really are the things that define how these things end up. It is obvious that there is a contract in place. They have asked you to complete work for them, you have done it. In return they need to pay you. Now, if they are not happy with the work, there is nothing which allows them to just pretend the contract didn't exist. They still have to pay you - you have done the work. Technically even if subjectively they don't like it - you still should be paid. If anything the onus is upon them for specifying exactly what they wanted before you started. Either way, you legally deserve the chance to change what they don't like. They can't just cut and run!
It really is simple stuff, in a legal sense anyway.
I really, really don't see how or why the solicitor advised you any differently. Maybe it wasn't a project that would be economic for them to take on? I don't know what motives they have. Either way, if you follow some polite, then more formal step you should get paid without a problem.
Forums | Speed, Plod & the Law | Top of Page | What's New | My Stuff