We've just completed an extension and were generally very pleased with both the work and the actual builders.
Their boss is a different matter though...
On completion of the work, the quote and the final staged invoice both stated that the site would be cleared and all materials removed.
During the clearing process I asked that a pack of bricks were moved from in front of the house as they were blocking the new garage entrance where they had been for 3 months.
One of the directors split the pack and moved them to the side. At no point was there any mention of ownership or collection of the bricks ( in fact we thought we'd paid for them).We did suggest they might be useful if there was any further work as the bricks were of the same appearance as those already used.
Invoices were paid and bricks ( plus several other items of potential further use) were left behind. We did not request this but they may be useful in the future.
Six weeks later we assumed that anything left behind had been "abandoned" and used 50, leaving 340.

We've just had a bill for £360 for the pack of bricks. We're reluctant to pay and have offered that they can be collected and either we'll pay for the 50 or he can have, in addition, 80 unused blue engineering bricks in lieu, which I bought.

We are withholding payment because,
They were left behind after they were meant to have cleared the site on completion,
They split the pack making collection by the merchant impossible
No mention of ownership or collection was ever discussed
They are free to collect the bricks (infact they are in the way)

The builder has replied demanding payment and said we wanted them.

Am I being unreasonable and do you have any advice?

Incidentally the value of the total work was approximately £160000.

Edited by stuartmmcfc on Wednesday 24th December 10:37

RobinOakapple

2,802 posts

143 months

Wednesday 24th December 2014
quotequote all
Have you had a reply yet to your offer? If so, what did it say? If not, why not wait until you do?

s55shh

523 posts

243 months

Wednesday 24th December 2014
quotequote all
Send him an invoice for storage of bricks at the same price less the ones you have used.

rb5er

11,657 posts

203 months

Wednesday 24th December 2014
quotequote all
If your bill was for materials and labour then they are his bricks, and he should do with them as he wishes.

If you asked to keep them then perhaps you should pay for them unless you have already in the invoice.

Someone over-ordered.

Maybe spilt the difference and meet them halfway for an easy life?

Squiggs

1,520 posts

186 months

Wednesday 24th December 2014
quotequote all
If the total cost of the job was £160000 then for either you or the builder to haggle over a few bricks priced at £360 seems a little petty to me.

stuartmmcfc

Original Poster:

8,775 posts

223 months

Wednesday 24th December 2014
quotequote all
Squiggs said:
If the total cost of the job was £160000 then for either you or the builder to haggle over a few bricks priced at £360 seems a little petty to me.
I'd agree but ...
After £160000 we're skint smile and we've gone off him after a few incidents.

Nightmare

5,279 posts

315 months

Wednesday 24th December 2014
quotequote all
our builder left behind:
6 acro props, 300 bricks, a 6 foot steel, 6 railway sleepers and a cement mixer!

someone pinched the mixer about 3 weeks after being left, and we gave the other bits away to people who knocked and asked for them.........builder (who we got on very well with) knew they were his issue to sort and was entirely happy they all vanished without further effort from him, no way on earth (with the exception of the mixer) would we have considered those things still his after a month of being left; and neither did he.

personally i think he's in the wrong and your offer for him to collect whats left and you pay the balance is more than fair

allergictocheese

1,290 posts

144 months

Wednesday 24th December 2014
quotequote all
Are the bricks part of the original contract/ invoice?

If not, was there any communication where you offered to keep/ buy the bricks?

Bear in mind that, depending on the circumstances, by using some of the bricks it may be that you've affirmed a contract to buy them by your conduct.

Considering you've spent over a hundred grand and that you admit the bricks might come in handy, and its Christmas, why not just offer a reasonable price and buy them?

stuartmmcfc

Original Poster:

8,775 posts

223 months

Wednesday 24th December 2014
quotequote all
After several emails back and forth today, he's confirmed theres been a "mix up" at his end and we won't be charged and he'll remove the bricks in the new year.
Tbh he's been such a prick, causing several problems for us by his actions that I dont really want to be generous to him anymore.
The 2 guys who did the majority of the work have fallen out with him, not been paid, and left to do their own jobs.

pinchmeimdreamin

10,915 posts

249 months

Wednesday 24th December 2014
quotequote all
allergictocheese said:
Considering you've spent over a hundred grand and that you admit the bricks might come in handy, and its Christmas, why not just offer a reasonable price and buy them?
Considering the OP had given them £160k worth of work and they had left the bricks on his property for getting on 5 months and its christmas how about they just say, "sorry our mistake we will claim the remaining bricks ASAP" ?

CMYKguru

3,017 posts

206 months

Wednesday 24th December 2014
quotequote all
You've paid them £160k and they're kicking off about a few hundred quid of bricks.

A decent brick is what about £2.

I'd say something like " You have one week to collect the bricks or else you'll be charged storage as they're on my property"

shake n bake

2,221 posts

238 months

Wednesday 24th December 2014
quotequote all
Who agreed to buy the bricks? You or the builder? Said party will pay the invoice.

Wacky Racer

41,401 posts

278 months

Wednesday 24th December 2014
quotequote all
Just get him to pick the bricks up, get's them out of your way and move on.

Enjoy your new extension...smile

stuartmmcfc

Original Poster:

8,775 posts

223 months

Thursday 25th December 2014
quotequote all
Thanks for the replys guys. Nearly all the questions were answered in the original post and the situation has been resolved in my last post.