Planned power outage during lockdown...
Planned power outage during lockdown...
Author
Discussion

BrettMRC

Original Poster:

5,997 posts

189 months

Thursday 4th June 2020
quotequote all
Possibly not the right area...

One of the local landowners is building a new farm, in a few weeks time they will be connecting the transformer to the mains. As a result SSE have informed us that the power will be out for c4 hours on a Monday between 10:00 and 14:00 apprx.

I have called up the SSE helpline to see if this time or date can be moved given a lot of us are now WFH on a more or less permanent basis; I was told that these things are arranged months in advance and moving it is practically impossible/unheard of..they gave me the direct number for the project manager but he never answers/calls back.

Normally I would suck it up and move on, however my thoughts now are:

  • Given the pandemic and people WFH, why can't it be done right at the beginning or end of the day? (ie, not right over the busiest parts)
  • Why not a weekend?
  • If it has to go ahead, do the impacted people have the right to expect some kind of redress? (again, I'm not normally on the compensation bandwagon - but why should I and the other 60 impacted properties lose a days holiday/productivity because of a new connection?)
  • Am I being unreasonable?
Thoughts/abuse/spelling & grammar corrections all happily received!

Edited by BrettMRC on Thursday 4th June 14:48


Edited by BrettMRC on Thursday 4th June 14:48

WonkeyDonkey

2,582 posts

132 months

Thursday 4th June 2020
quotequote all
Fully charge your laptop and use your phone as a hot spot.

Pothole

34,367 posts

311 months

Thursday 4th June 2020
quotequote all
BrettMRC said:
Possibly not the right area...

One of the local landowners is building a new farm, in a few weeks time they will be connecting the transformer to the mains. As a result SSE have informed us that the power will be out for c4 hours on a Monday between 10:00 and 14:00 apprx.

I have called up the SSE helpline to see if this time or date can be moved given a lot of us are now WFH on a more or less permanent basis; I was told that these things are arranged months in advance and moving it is practically impossible/unheard of..they gave me the direct number for the project manager but he never answers/calls back.

Normally I would suck it up and move on, however my thoughts now are:

  • Given the pandemic and people WFH, why can't it be done right at the beginning or end of the day? (ie, not right over the busiest parts)
  • Why not a weekend?
  • If it has to go ahead, do the impacted people have the right to expect some kind of redress? (again, I'm not normally on the compensation bandwagon - but why should I and the other 60 impacted properties lose a days holiday/productivity because of a new connection?)
  • Am I being unreasonable?
Thoughts/abuse/spelling & grammar corrections all happily received!

Edited by BrettMRC on Thursday 4th June 14:48


Edited by BrettMRC on Thursday 4th June 14:48
You're not on the compo bandwagon but you're already exaggerating for effect. Or do you actually only work for 4 hours over lunchtime? On second thoughts, fk 'me. Kick up a massive fuss and get it moved to a time which is more convenient to you. It's not like farms are useful, is it? You're FAR more important than mere food production!

DoubleD

22,154 posts

137 months

Thursday 4th June 2020
quotequote all
Can you not do 3-4 hours work before 10am? Then have a break and do the rest after 2pm?

Dg504

363 posts

192 months

Thursday 4th June 2020
quotequote all
The perfect excuse for a long cycle or walk and you’re complaining?!

Charged laptop and hotspot if you’re that important/drive it to somewhere nice and enjoy some fresh air

rscott

17,481 posts

220 months

Thursday 4th June 2020
quotequote all
BrettMRC said:
Possibly not the right area...

One of the local landowners is building a new farm, in a few weeks time they will be connecting the transformer to the mains. As a result SSE have informed us that the power will be out for c4 hours on a Monday between 10:00 and 14:00 apprx.

I have called up the SSE helpline to see if this time or date can be moved given a lot of us are now WFH on a more or less permanent basis; I was told that these things are arranged months in advance and moving it is practically impossible/unheard of..they gave me the direct number for the project manager but he never answers/calls back.

Normally I would suck it up and move on, however my thoughts now are:

  • Given the pandemic and people WFH, why can't it be done right at the beginning or end of the day? (ie, not right over the busiest parts)
  • Why not a weekend?
  • If it has to go ahead, do the impacted people have the right to expect some kind of redress? (again, I'm not normally on the compensation bandwagon - but why should I and the other 60 impacted properties lose a days holiday/productivity because of a new connection?)
  • Am I being unreasonable?
Thoughts/abuse/spelling & grammar corrections all happily received!

Edited by BrettMRC on Thursday 4th June 14:48


Edited by BrettMRC on Thursday 4th June 14:48
Do it at the weekend when more people will be at home and they'll have to pay overtime to the works crew who almost certainly don't normally work weekends?


irocfan

48,995 posts

219 months

Thursday 4th June 2020
quotequote all
DoubleD said:
Can you not do 3-4 hours work before 10am? Then have a break and do the rest after 2pm?
if he's anything like me he can't - there'll be reports and deadlines to be run/received/posted. TBF the mobile hot-spot isn't a bad shout

BrettMRC

Original Poster:

5,997 posts

189 months

Thursday 4th June 2020
quotequote all
Pretty much the sort of responses I was expecting! hehe

The issue is that I have to move a load of meetings etc that impact a lot of people beyond SSE's scope, just so farmer can have his power connected by the end of lunch?

I already work from 07:00 most days.

Just don't like being told what will happen, with no consultation, so that someone can add another farm to their portfolio.

TheInternet

5,230 posts

192 months

Thursday 4th June 2020
quotequote all
irocfan said:
TBF the mobile hot-spot isn't a bad shout
That might depend if the relevant mast is fed by the same supply.

TGTiff

497 posts

213 months

Thursday 4th June 2020
quotequote all
I've been working from home since lockdown just using mobile hotspot, no problem even in "Darkest Cumbria".

OscarIndia

1,216 posts

201 months

Thursday 4th June 2020
quotequote all
BrettMRC said:
Pretty much the sort of responses I was expecting! hehe

The issue is that I have to move a load of meetings etc that impact a lot of people beyond SSE's scope, just so farmer can have his power connected by the end of lunch?

I already work from 07:00 most days.

Just don't like being told what will happen, with no consultation, so that someone can add another farm to their portfolio.
So which weekday would suit sir best?

BrettMRC

Original Poster:

5,997 posts

189 months

Thursday 4th June 2020
quotequote all
A weekday in 2023 when this has all blown over? biggrin

I'm happy to hotspot etc, but it's still a PITA, especially as it will probably overrun.

Guess I'm ****ed off that once again the landowner with the big money gets to do what he likes and the ones that live here can suck it up as usual.

Sheepshanks

40,992 posts

148 months

Thursday 4th June 2020
quotequote all
BrettMRC said:
The issue is that I have to move a load of meetings etc that impact a lot of people
You said they'd given a few weeks notice - have you really got a load of meeting with a lot of people arranged that far in advance, and crammed into a 4 hr period?

If it's that vital then don't WFH that day.

rscott

17,481 posts

220 months

Thursday 4th June 2020
quotequote all
BrettMRC said:
A weekday in 2023 when this has all blown over? biggrin

I'm happy to hotspot etc, but it's still a PITA, especially as it will probably overrun.

Guess I'm ****ed off that once again the landowner with the big money gets to do what he likes and the ones that live here can suck it up as usual.
You'd have hated me then (even though I'm a house owner with not much money) .. Supplier turned off electricity to half our village for 8 hours to sort out our supply issues last year.. Our power didn't go off at all.

BrettMRC

Original Poster:

5,997 posts

189 months

Thursday 4th June 2020
quotequote all
Sheepshanks said:
BrettMRC said:
The issue is that I have to move a load of meetings etc that impact a lot of people
You said they'd given a few weeks notice - have you really got a load of meeting with a lot of people arranged that far in advance, and crammed into a 4 hr period?

If it's that vital then don't WFH that day.
I don't have a choice sadly, WFH unless I am at risk in the property... nature of my role means that I cannot plan that far in advance as it involves a lot of incident response etc.

Will probably take it as a days leave.

  1. wasteofathreadreally

DoubleD

22,154 posts

137 months

Thursday 4th June 2020
quotequote all
BrettMRC said:
Guess I'm ****ed off that once again the landowner with the big money gets to do what he likes and the ones that live here can suck it up as usual.
I'm guessing this is the real reason for your annoyance?


So what is stopping you from working from the office for 1 day?

surveyor

18,690 posts

213 months

Thursday 4th June 2020
quotequote all
TheInternet said:
irocfan said:
TBF the mobile hot-spot isn't a bad shout
That might depend if the relevant mast is fed by the same supply.
If they have had the appropriate notice (And assuming unlike a site I saw a few weeks ago where the supplier had sent the notice to the mast and the postman had wedged it in the gate), the operator is aware they should sort a generator for the day.

V8fan

8,520 posts

297 months

Thursday 4th June 2020
quotequote all
The advice is, and was to WFH 'if possible.'

In my experience planned outages often over-run to so don't open your fridge or freezer door either, although they'd be fine for 8 hrs ish I'd have thought.

Chrisgr31

14,275 posts

284 months

Thursday 4th June 2020
quotequote all
surveyor said:
the operator is aware they should sort a generator for the day.
And there is the OPs solution. Plug an extension cable in to the mobile companies generator and run it home! 😂🤣😂

Thisonepotato

843 posts

180 months

Thursday 4th June 2020
quotequote all
Stupid question but would would you do if you woke up that day to a 4 hour power cut?