soil pipe/chain cutter
Discussion
x 7usc said:
thanks guys i would normally cut these with a grinder but 1 i have limited space and 2 the pipe in in a riser 5 storeys up on an old block of flats, im not sure if there is anything dry and flamable down there 
Then refer to the RAMS
Method Statement / Risk Assesment
Surley this task should have been taken into account before work commenced.
If all else fails - hacksaw
SVTRick said:
x 7usc said:
thanks guys i would normally cut these with a grinder but 1 i have limited space and 2 the pipe in in a riser 5 storeys up on an old block of flats, im not sure if there is anything dry and flamable down there 
Then refer to the RAMS
Method Statement / Risk Assesment
Surley this task should have been taken into account before work commenced.
If all else fails - hacksaw
im thinking its probably going to come to hacksaw option (at extra cost)
SVTRick said:
What about go down to the next collar and remove a section by percussive means then replace with UPVC or Timesaver if you wanna keep to iron pipe in riser ?
next socket down is in the flat below, plastered in, but you have given me an idea.i can just about make it work for falls if i remove the cast branch i have and insert a UPVC corner branch in the stack.
thanks Rick & everyone else
Sorted