Any architects ?
Author
Discussion

z1000

Original Poster:

649 posts

267 months

Monday 23rd May 2005
quotequote all
This is probably beneath an architect , but anyway..

Having received ludicrous quotes for a concrete slab for a shed/workshop[small]/distillery[/small](about £1200 for 3000mm X 5000mm) I have been pondering cheaper alternatives.

What I have come up with is : concrete piles of about 200mm in diameter , 10 in total spaced in 2 rows 3000mm apart , and at 1000mm intervals ::::: < like that! Span the 3000mm interval with a lintel , and then after laying a damp proof membrane on the lintels , simply span the 1 metre gaps with floor joists ( correct size and spacing from your build reg books?) to produce a reasonably solid floor.

Does this sound like a neat , cheap solution ?
I can hit chalk about 1 metre deep and would propose to auger the holes. Total volume of concrete is circa 0.3 metres.

Any comments ?

mybrainhurts

90,809 posts

284 months

Monday 23rd May 2005
quotequote all
z1000 said:

What I have come up with is : concrete piles....


Not sure if you want a surgeon or stonemason for that little problem......

trumpet600

3,527 posts

260 months

Monday 23rd May 2005
quotequote all
John

Do it yourself you lazy git. Get your missus to man the mixer, and the kids on the wheelborrow and you'll have it done in no time.

Are you up for a trackday in the next month?

Tony

rsvmilly

11,288 posts

270 months

Monday 23rd May 2005
quotequote all
Do it yourself.

Hire a mini digger to dig the foundations with. Think how much fun that'll be, playing with a digger.

Then just a few mates to barrow 3 cubic metres of concrete to the slab.

Bob's your auntie's live-in lover!

B17NNS

18,506 posts

276 months

Monday 23rd May 2005
quotequote all
Tony is right.

Hire a mixer, shutter of the required area, order a few bags of sand/ballast, some cement and do it yourself over the weekend.

Alteratively shutter of the required area. Order the required amount of readymix (the readymix company will tell you how much you need based on width x length x depth of the slab.

Get a few mates round with barrows, get your missus on BBQ and beer duty and have it done in an afternoon.

Save yourself a fortune and a lot less hassle than the pilings/joists idea.

z1000

Original Poster:

649 posts

267 months

Monday 23rd May 2005
quotequote all
Hi Tony ! Am doing it myself , just think my simple solution sounds less work

Trackday ? Would need to check funds after Le Mans , personally I'm not going on a corporate freebie

Actually , you are an architect aren't you ?

z1000

Original Poster:

649 posts

267 months

Monday 23rd May 2005
quotequote all
B17NNS said:
Tony is right.

Hire a mixer, shutter of the required area, order a few bags of sand/ballast, some cement and do it yourself over the weekend.

Alteratively shutter of the required area. Order the required amount of readymix (the readymix company will tell you how much you need based on width x length x depth of the slab.

Get a few mates round with barrows, get your missus on BBQ and beer duty and have it done in an afternoon.

Save yourself a fortune and a lot less hassle than the pilings/joists idea.


I am doing it myself! 3m X 5m x whatever depth ,say 200 mm minimum with hardcore = 3 cubic metres of soil to dig thats 6 cubic metres when its dug up (IIRC)Thats a skipful to barrow 200 feet , and 2 cubic metres of concrete to barrow back the other way.

The time you are allowed to lay the concrete by a firm like readymix is prohibitive (so many mins per Cubic metre)

trumpet600

3,527 posts

260 months

Monday 23rd May 2005
quotequote all
you've spent longer doing the calculations than it would take to do the job.

trumpet600

3,527 posts

260 months

Monday 23rd May 2005
quotequote all
And don't forget that lardy bro-in-law could give you a hand

z1000

Original Poster:

649 posts

267 months

Monday 23rd May 2005
quotequote all

mechsympathy

58,602 posts

284 months

Monday 23rd May 2005
quotequote all
z1000 said:

Thats a skipful to barrow 200 feet , and 2 cubic metres of concrete to barrow back the other way.


Well that explains the quote. I'd go with the piles idea simply because of the amount of labour involved if you don't. I'd be tempted (as a non-architect/engineer) to reduce the span on the joists and put in 3 rows.

B17NNS

18,506 posts

276 months

Monday 23rd May 2005
quotequote all
Some basic calcs to help when estimating foundations...


2 x mates plus 8 x stella = 3 cubic metres of soil dug and moved to skip

2 x mates (use different mates to equation above as the initial 8 x stella will have reduced their effective working capacity) plus 8 x stella = 2 cubic meters of concrete mixed, poured and levelled.

The hardcore element is perhaps a little more difficult to calculate but as a rule of thumb try this.

1 x mate plus 1 x BBQ'd steak (+ 2 x stella) should be suffuient for your needs.

z1000

Original Poster:

649 posts

267 months

Monday 23rd May 2005
quotequote all

Incorrigible

13,668 posts

290 months

Monday 23rd May 2005
quotequote all
I'm in Sussex and can lend you a mixer if you like

r8bwt

167 posts

256 months

Monday 23rd May 2005
quotequote all
Im currently working as a arch engineer, working for my chartership to the MCIOB, And I fully agree with everything thats been said on here. If it's only single story, and just birck/block. Do it yourself dig the trench, and fill with concrete then lay the membrane then cast the floor. No need for the floor to be structural either. As long as you have the founds for the brickwork the floor can be laid at a later date.

Any more advice, please don't hesitate to contact me

z1000

Original Poster:

649 posts

267 months

Monday 23rd May 2005
quotequote all
Thanks for the offer , I can get my hands on one quite easily though

trumpet600

3,527 posts

260 months

Monday 23rd May 2005
quotequote all
I'm just down the road. Let me know when you're doing the work and I'll make sure I have something else planned that weekend

angrys3owner

15,855 posts

258 months

Monday 23rd May 2005
quotequote all
sounds like a bloody good excuse to spend a fortune hiring a mini digger and a mini dump truck for a long weekend to me!

z1000

Original Poster:

649 posts

267 months

Monday 23rd May 2005
quotequote all
r8bwt said:
Im currently working as a arch engineer, working for my chartership to the MCIOB, And I fully agree with everything thats been said on here. If it's only single story, and just birck/block. Do it yourself dig the trench, and fill with concrete then lay the membrane then cast the floor. No need for the floor to be structural either. As long as you have the founds for the brickwork the floor can be laid at a later date.

Any more advice, please don't hesitate to contact me


Cheers r8bwt. It's only going to be a timber construction , 4x2's , sheet clad type of thing. Do you think a 3 metre span is ok ? What section lintel , and what section /spacing for the floor joists ? (1 metre span)