Planning permission timeframes?
Discussion
Howitzer said:
For anyone in the industry or has had to get planning permission for their places etc.
How long from the initial application to the agreement being made did it take you?
Dave!
350m2 steading conversion in Aberdeenshire, no major issues, took 7 months. Building warrant about a year How long from the initial application to the agreement being made did it take you?
Dave!

Busamav said:
For a straight forward application , the council have to determine the application in 8 weeeks .
They are obliged to determine minor applications within 8 weeks from the date of registration (which isn't quite the same as the date of application - you should have a written confirmation of registration which gives the 'start' date).Major applications are allowed 13 weeks.
In either case, if they haven't determined the application within the appropriate period, you are entitled to appeal on the grounds of non-determination.
Our bog standard bungalow took 9months including 1 rejection (garage in the rear garden for reasons unknown was not acceptable, even though my archtiect pointed out as its in the rear garden we can build it when we finished and signed off with no pp needed!!)
It took them 4 weeks to 'register' the application then 12 weeks to actualy look at it!
Suffolk CC
It took them 4 weeks to 'register' the application then 12 weeks to actualy look at it!
Suffolk CC
jollygreen said:
Howitzer said:
For anyone in the industry or has had to get planning permission for their places etc.
How long from the initial application to the agreement being made did it take you?
Dave!
350m2 steading conversion in Aberdeenshire, no major issues, took 7 months. Building warrant about a year How long from the initial application to the agreement being made did it take you?
Dave!

Sam_68 said:
Busamav said:
For a straight forward application , the council have to determine the application in 8 weeeks .
They are obliged to determine minor applications within 8 weeks from the date of registration (which isn't quite the same as the date of application - you should have a written confirmation of registration which gives the 'start' date).Major applications are allowed 13 weeks.
In either case, if they haven't determined the application within the appropriate period, you are entitled to appeal on the grounds of non-determination.
Make sure you add something weird to the design that you don't actually want so that they'll make a fuss over that and not something you really care about. Planning depts have to object to something so you might as well make it easy for them.
My dad used to add random turrets to his designs so that he could later remove them when the planning dept objected. The planning dept then considered that a job well done and approved the basic design without a problem. On the applications san-turrets they had to find something to object to (usually windows or something silly) which caused him no end of problems.
My dad used to add random turrets to his designs so that he could later remove them when the planning dept objected. The planning dept then considered that a job well done and approved the basic design without a problem. On the applications san-turrets they had to find something to object to (usually windows or something silly) which caused him no end of problems.
Edited by theaxe on Tuesday 6th January 16:34
Mandat said:
That is why some sneaky councils will refuse an application if they are running of time and they will then have another 8 weeks when you have to re-submit the application.
Unfortunately, they have to give reasons for the refusal, in which case, if you are confident that there was nothing wrong with the design you simply resubmit and submit an appeal in parallel. It causes them 5 times as much work and gives them a black mark on their performance targets, if the appeal is upheld. If you think an application is heading this way, make it clear to them that you will appeal... it focuses their mind and very few planners will issue an unwarranted refusal if they know that the reasons given will need to stand up to the scrutiny of the Appeals Inspectorate.To be fair, the opposite is often true of most authorities, if you talk to them... if there are outstanding issues to be resolved, either with the design or with the consultation process, they will allow you to runn the application to within the 11th hour of the deadline, to get as much sorted as possible, then withdraw and resubmit to re-set the clock. In this way, you can both avoid the appeal process, you get the chance to resolve any outstanding issues and the re-submitted application is fast-tracked through as smoothly as possible when it goes back in.
Edited by Sam_68 on Tuesday 6th January 20:40
Good luck....
Councils are around 6-8 weeks for permission, but your architect will know better how good your local area are.
We were 6 weeks for permission for our humble 27m2 extension, but having an experienced builder helps. Ours said most builders charge about £1000 per m2 for dwelling extensions (the house) slightly less for non dwelling (the garage)
Councils are around 6-8 weeks for permission, but your architect will know better how good your local area are.
We were 6 weeks for permission for our humble 27m2 extension, but having an experienced builder helps. Ours said most builders charge about £1000 per m2 for dwelling extensions (the house) slightly less for non dwelling (the garage)
theaxe said:
Make sure you add something weird to the design that you don't actually want so that they'll make a fuss over that and not something you really care about. Planning depts have to object to something so you might as well make it easy for them.
My dad used to add random turrets to his designs so that he could later remove them when the planning dept objected. The planning dept then considered that a job well done and approved the basic design without a problem. On the applications san-turrets they had to find something to object to (usually windows or something silly) which caused him no end of problems.
We applied for a side extension on our last house - architect got his crayons out and went for a chat with the planner to see what they thought before actually submitting something - "no, no, no - no, you can't do that" etc etc. Seemingly no chance.My dad used to add random turrets to his designs so that he could later remove them when the planning dept objected. The planning dept then considered that a job well done and approved the basic design without a problem. On the applications san-turrets they had to find something to object to (usually windows or something silly) which caused him no end of problems.
Edited by theaxe on Tuesday 6th January 16:34
Thought to hell with it, and redrew it as big as we could, stuck a conservatory on the back for good measure, submitted it and it flew through - under a different planning officer.
No rhyme or reason, no logic to them - but the turrets idea is a good one