Hi all,
I'm having a car built for me by a given company, which particular one doesn't really matter. Various soft deadlines have wafted past, communication is not quite what I would have hoped, and I am beginning to wonder if said company is beginning to take the mick and might need a big of a poke.
In particular, they ate claiming to have applied for IVA around 1st June, but are yet to recieve a date. Appreciate this may vary by test centre, but do any PHers know if this sort of time frame is par for the course (it seems like quite a while to not even have a date yet) or perhaps a sign that something may be awry?
Thanks in advance
I'm having a car built for me by a given company, which particular one doesn't really matter. Various soft deadlines have wafted past, communication is not quite what I would have hoped, and I am beginning to wonder if said company is beginning to take the mick and might need a big of a poke.
In particular, they ate claiming to have applied for IVA around 1st June, but are yet to recieve a date. Appreciate this may vary by test centre, but do any PHers know if this sort of time frame is par for the course (it seems like quite a while to not even have a date yet) or perhaps a sign that something may be awry?
Thanks in advance
I passed IVA on the second attempt 2 weeks ago.
My timeline was approx. 1 week from sending the application to getting a call to pay for it.
3 weeks delay for the paperwork to be processed by the DVLA and passed to the local test centre.
3 days for the test centre to call and arrange apt.
2 weeks from call to test.
2 weeks from fail to pass.
4 days from pass to reg & tax from local DVLA office.
Sounds a long time from 1st June.
My timeline was approx. 1 week from sending the application to getting a call to pay for it.
3 weeks delay for the paperwork to be processed by the DVLA and passed to the local test centre.
3 days for the test centre to call and arrange apt.
2 weeks from call to test.
2 weeks from fail to pass.
4 days from pass to reg & tax from local DVLA office.
Sounds a long time from 1st June.
Ivathrowaway83 said:
Thanks for the info guys - looks like company needs a prod to chase the DVLA a bit harder.
Thanks again,
Not DVLA, VOSA.Thanks again,
Far to long a wait to be believable.
2 weeks for the paperwork to be processed.
Couple of days for it to arrive at the test station.
Couple of days for them to contact you and offer a test date.
That date may be 2-3 weeks forward.
Contacted my local station today to book a couple of retests....Tuesday and Wednesday next week.
Steve