16 unit development site
Discussion
I have been approached by a friend who has agreed in principle with local Planners, for a knock-down of his cottage and build 16 units - assume small starters of 2bed type.
They also said needs to be a 1:5 of 'cheap / shared ownership' units - whatever the terminology is.
Where to start - the area is low cost, so new 2bed terraces are in GBP 125-150k range.
How can I build a hi-level business plan, with ballpark numbers and a little sensitivity analysis ?
The financial and practical implications of these '3-4 units' at below market price or rent ?
The plot has road access, and is surrounder by 2-3 bed 1950s or newer properties nothing too desirable, hence local planners want as many units as possible.
Cheers for any guidance, links, etc.
Big Ant
They also said needs to be a 1:5 of 'cheap / shared ownership' units - whatever the terminology is.
Where to start - the area is low cost, so new 2bed terraces are in GBP 125-150k range.
How can I build a hi-level business plan, with ballpark numbers and a little sensitivity analysis ?
The financial and practical implications of these '3-4 units' at below market price or rent ?
The plot has road access, and is surrounder by 2-3 bed 1950s or newer properties nothing too desirable, hence local planners want as many units as possible.
Cheers for any guidance, links, etc.
Big Ant
lots of questions:
- do they have an architect?
- do they have drawings/ plans for what he's going to build?
- do they know what services are required to the site? (and cost!)
- do they have a quantity surveyor to prepare take offs?
- will they be building these themselves or employing a contractor to carry out the work?
- or do they have any knowledge of setting up sub-contracts for the works?
sorry if these all seem a bit basic questions to be asking, but for a project of 16 homes, i feel they really should get an architect/QS/contractor on-board to help with the development of the project.
the architect can help/sort out all the planning required, help with permits, permissions, plans for the properties, what regs etc... all need to be adhered too.
a QS will help prepare a take off for each of the propeties, this will allow you to divide up the works and issue tenders to sub-contractors for pricing. this way you will know exactly what each trade is going to do for you, that way you know what your paying for and can compare like for like in pricing.
getting a good contractor to build the homes would also be needed if they dont know anything about building. they will see the project through the construction phase and sort out all the different trades/ planning etc... required for the build.
yes getting all these people involved will reduce the profits, but they can greatly reduce the headaches! sorry if i've dumbed it down a bit too much, but i dont know what knowledge these people have for starting a development like this.
- do they have an architect?
- do they have drawings/ plans for what he's going to build?
- do they know what services are required to the site? (and cost!)
- do they have a quantity surveyor to prepare take offs?
- will they be building these themselves or employing a contractor to carry out the work?
- or do they have any knowledge of setting up sub-contracts for the works?
sorry if these all seem a bit basic questions to be asking, but for a project of 16 homes, i feel they really should get an architect/QS/contractor on-board to help with the development of the project.
the architect can help/sort out all the planning required, help with permits, permissions, plans for the properties, what regs etc... all need to be adhered too.
a QS will help prepare a take off for each of the propeties, this will allow you to divide up the works and issue tenders to sub-contractors for pricing. this way you will know exactly what each trade is going to do for you, that way you know what your paying for and can compare like for like in pricing.
getting a good contractor to build the homes would also be needed if they dont know anything about building. they will see the project through the construction phase and sort out all the different trades/ planning etc... required for the build.
yes getting all these people involved will reduce the profits, but they can greatly reduce the headaches! sorry if i've dumbed it down a bit too much, but i dont know what knowledge these people have for starting a development like this.
Thanks Malks, and as for dumbing down, I am happy to learn, so no worries.
Infact that line of questions for me to present to my friend is ideal, as will trigger alsorts of alerts in my head.
I was trying to tackle the problem upside down - if i can draft a high level financial plan, does it make sense to engage at all.
(i.e. 16 units x 125k = 2m gross, less fees & financing charges, less infrastructure, less build costs and selling costs.....could leave not a lot !)
Funny you dream of building in a garden plot - one comes along, and suddenly it all looks a tad difficult. But you are right, hiring some qualified experienced local architects is a must.
The friend thinks that as his main residence, there wont be personal or CGT to pay....another little topic to explore.
Cheers.
Infact that line of questions for me to present to my friend is ideal, as will trigger alsorts of alerts in my head.
I was trying to tackle the problem upside down - if i can draft a high level financial plan, does it make sense to engage at all.
(i.e. 16 units x 125k = 2m gross, less fees & financing charges, less infrastructure, less build costs and selling costs.....could leave not a lot !)
Funny you dream of building in a garden plot - one comes along, and suddenly it all looks a tad difficult. But you are right, hiring some qualified experienced local architects is a must.
The friend thinks that as his main residence, there wont be personal or CGT to pay....another little topic to explore.
Cheers.
i think getting an architect involved early doors is the best plan before even considering this type of project. if your friend isnt clued up on all this they really need professional advice!
he may have planning consent in principle, but sometime these things can take ages to actually get through, how quickly does he need this to go from start to finish? months or years?
how much capital does this person have for upfront costs? architects, QS, legal fees etc... will prob all need to be getting paid early on, and banks arent exactly wanting to lend on self build houses never mind funding a new development. so really that may need to be done through a business, which then effects the CGT/tax situation as he wont be doing it personally.
also will these properties sell quickly? what happens if only half get sold quickly, can he afford to keep paying the development while half the houses sit waiting to be sold?
another option that he may want to consider is getting the planning permissions all complete and selling off the land to a developer and not worrying about the construction at all.
he may have planning consent in principle, but sometime these things can take ages to actually get through, how quickly does he need this to go from start to finish? months or years?
how much capital does this person have for upfront costs? architects, QS, legal fees etc... will prob all need to be getting paid early on, and banks arent exactly wanting to lend on self build houses never mind funding a new development. so really that may need to be done through a business, which then effects the CGT/tax situation as he wont be doing it personally.
also will these properties sell quickly? what happens if only half get sold quickly, can he afford to keep paying the development while half the houses sit waiting to be sold?
another option that he may want to consider is getting the planning permissions all complete and selling off the land to a developer and not worrying about the construction at all.
A plus one for getting the architect/planning advisor on board and looking at selling once full PP is achieved. You're still hopefully likely to walk out with a significant gain without a lot of the pain.
16 units is a significant project to manage and equally a major project to fund. That said you should be able to sell off the affordable portion prior to building to a housing association thus alleviating some of that risk.
16 units is a significant project to manage and equally a major project to fund. That said you should be able to sell off the affordable portion prior to building to a housing association thus alleviating some of that risk.