Anyone on this board with knowledge on the finer points of dilaps?
I am landlord of a several shops, one of which was rented to local council. Council exercised break-clause terminating lease on 30 November and handed back keys 27 Nov. Surveyors acting for both parties inspected premises on 1 Dec. and agreed condition was unacceptable and my surveyor would draw up Schedule of Dilaps. Wants were relatively minor, but works were not finally completed and keys returned until 1st week of April.
Allowing 3 months void rates exemption meant I incurred 30 days rates liability for year to 1 April 2009. I refused to pay, arguing Council were liable, as it took excessive time to complete repairs. (Also lost opportunity of short term let in Dec due to outstanding works.)
In July council issued summons and obtained Liability Order (since suspended) while I was abroad for 3 weeks (issued summons day after I left country with Hearing date 2 days before my return – flight tickets to prove.) Lengthy correspondence then ensued in which I argued, as the Council was a party to the dispute the matter should be referred back for the Court to decide liability. But council refuses, instead in its latest letter stated, ”Once lease expired council had relinquished its obligation to occupy and for rating purposes landlord is then responsible. The additional works did not make council responsible for rates, and it could not reoccupy premises again after end of lease.”
Do I have a valid argument claiming council took excessive time with repairs and therefore liable for rates or am I on a hiding-to-nothing here? I would have thought obligation was for tenant to ensure premises were handed back in fit state BY lease expiry date. Had a lump sum been agreed for repairs, it would have included a sum for loss of rent.
I am landlord of a several shops, one of which was rented to local council. Council exercised break-clause terminating lease on 30 November and handed back keys 27 Nov. Surveyors acting for both parties inspected premises on 1 Dec. and agreed condition was unacceptable and my surveyor would draw up Schedule of Dilaps. Wants were relatively minor, but works were not finally completed and keys returned until 1st week of April.
Allowing 3 months void rates exemption meant I incurred 30 days rates liability for year to 1 April 2009. I refused to pay, arguing Council were liable, as it took excessive time to complete repairs. (Also lost opportunity of short term let in Dec due to outstanding works.)
In July council issued summons and obtained Liability Order (since suspended) while I was abroad for 3 weeks (issued summons day after I left country with Hearing date 2 days before my return – flight tickets to prove.) Lengthy correspondence then ensued in which I argued, as the Council was a party to the dispute the matter should be referred back for the Court to decide liability. But council refuses, instead in its latest letter stated, ”Once lease expired council had relinquished its obligation to occupy and for rating purposes landlord is then responsible. The additional works did not make council responsible for rates, and it could not reoccupy premises again after end of lease.”
Do I have a valid argument claiming council took excessive time with repairs and therefore liable for rates or am I on a hiding-to-nothing here? I would have thought obligation was for tenant to ensure premises were handed back in fit state BY lease expiry date. Had a lump sum been agreed for repairs, it would have included a sum for loss of rent.
Your on a hiding to nothing, if you are challenging the Business Rates department. Legally when the property is handed back to you the rates become your responsibility.
Some Surveyors when acting for the landlord and agreeing dilapidation works will ask for the Business Rates for the duration of the lease. More helpfully leases sometimes provide for this also.
If it was not agreed then you are just storing trouble up for yourself.
Some Surveyors when acting for the landlord and agreeing dilapidation works will ask for the Business Rates for the duration of the lease. More helpfully leases sometimes provide for this also.
If it was not agreed then you are just storing trouble up for yourself.
The lease is silent regards rates, but from what davidjpowell says it sounds like I'll have to pay up and shut up. Still, at least Rates Department dropped the bailiff's charges, although not council's £50 summons costs. (Nice little earner that - last time I received rates summons there were probably a 1,000 other folk there, each with their £50 summons.
Just to confirm that you did take the keys back on 1 November and the council did not retain them to do the work?
If the Council had retained the keys and were doing the work I would be tempted to run the argument that they were in occupation / control of the premises as opposed to you marketing the premises and allowing access when required. Ultimately I think it's unlikely that you would be able to win, even if this is the case.
If the Council had retained the keys and were doing the work I would be tempted to run the argument that they were in occupation / control of the premises as opposed to you marketing the premises and allowing access when required. Ultimately I think it's unlikely that you would be able to win, even if this is the case.
davidjpowell
As you gather from communications below relationship with tenant was not a happy one and even return of keys was problematical. But my agent received keys back on 28 Nov but keys were GIVEN BACK to council to carry out works, although we could still gain access carry out viewings.
27 Nov - Email to me from my surveyor
Council surveyor is concerned that if the keys are not with us before 30th Nov then we will say that they haven't vacated the premises and must continue for a further 3 months (periodic tenancy). Likewise, I've told him that with the attitude of the Council's solicitors over matters, they may try to argue that there are other implications as we've taken the keys back early.
To get round this, can you please provide me with a letter that I can email to surveyor confirming that if they give us the keys tomorrow afternoon then we will not pursue them for a continuation tenancy from 1st December.
In the meantime, I trust you will appreciate my concerns about taking keys back early given the Council's solicitors approach to matters in the past. I think there is a degree of mistrust on both sides.
(I don't think I picked up email in time to provide assurance I would not pursue continuation tenancy.)
28 Nov Email from my surveyor to council surveyor
Whilst I am awaiting my client to come back to me, could I equally suggest that you/the Council provide us with a letter confirming that if we do accept keys from you today then this will not be deemed as an early surrender of the lease and that all provisions & covenants, etc within the existing lease will continue until the time of contractual expiry. If I have this then I would be happy to take keys back from you, strictly on the basis that I am holding them as agent and am not accepting them in consideration of an early surrender of the lease.
As you gather from communications below relationship with tenant was not a happy one and even return of keys was problematical. But my agent received keys back on 28 Nov but keys were GIVEN BACK to council to carry out works, although we could still gain access carry out viewings.
27 Nov - Email to me from my surveyor
Council surveyor is concerned that if the keys are not with us before 30th Nov then we will say that they haven't vacated the premises and must continue for a further 3 months (periodic tenancy). Likewise, I've told him that with the attitude of the Council's solicitors over matters, they may try to argue that there are other implications as we've taken the keys back early.
To get round this, can you please provide me with a letter that I can email to surveyor confirming that if they give us the keys tomorrow afternoon then we will not pursue them for a continuation tenancy from 1st December.
In the meantime, I trust you will appreciate my concerns about taking keys back early given the Council's solicitors approach to matters in the past. I think there is a degree of mistrust on both sides.
(I don't think I picked up email in time to provide assurance I would not pursue continuation tenancy.)
28 Nov Email from my surveyor to council surveyor
Whilst I am awaiting my client to come back to me, could I equally suggest that you/the Council provide us with a letter confirming that if we do accept keys from you today then this will not be deemed as an early surrender of the lease and that all provisions & covenants, etc within the existing lease will continue until the time of contractual expiry. If I have this then I would be happy to take keys back from you, strictly on the basis that I am holding them as agent and am not accepting them in consideration of an early surrender of the lease.
I would question whether the break clause has been correctly activated if the Council had not done the works prior to the break date. Under the terms of a lot of leases that would mean that the break clause had not been activated correctly and the Landlord would argue that the lease remains in force.
However on the business rates issue: -
What is the rateable value of the property? Has it subsequently been let or is it still empty? What exactly were the works? How much did they cost? How much money i terms of rate payments are we talking about?
The problem I suspect is going to be arguing over who was in actual possession, and who was in beneficial possession. The Council could argue that you were in beneficial occupation because you were permitted to show potential new tenants around. However you stated that you missed out on short term pre Christmas let? Why was this? You could serve a proposal on the Valuation Officer asking for it to be taken out of rating during the works. He may well refuse, however there has been a very helpful case on this at Valuation Tribunal recently (which I suspect the VO will appeal). Alternatively or concurrently you may like to argue that you were prevented from occupying the property under Health and Safety legislation. If you had a letter from the COuncil stating that the works were not going to be completed before your potential sublet this might be an easier case to run.
However in reality I guess the amount of money involved is relatively minor and not worth pursuing. Another approach is to suggest to the Council that the property was vacant from 1 Nov to date when works started, and then occupied during the works, and then empty once the works were completed. Giving you a three month exemption at the end of the works.
However on the business rates issue: -
What is the rateable value of the property? Has it subsequently been let or is it still empty? What exactly were the works? How much did they cost? How much money i terms of rate payments are we talking about?
The problem I suspect is going to be arguing over who was in actual possession, and who was in beneficial possession. The Council could argue that you were in beneficial occupation because you were permitted to show potential new tenants around. However you stated that you missed out on short term pre Christmas let? Why was this? You could serve a proposal on the Valuation Officer asking for it to be taken out of rating during the works. He may well refuse, however there has been a very helpful case on this at Valuation Tribunal recently (which I suspect the VO will appeal). Alternatively or concurrently you may like to argue that you were prevented from occupying the property under Health and Safety legislation. If you had a letter from the COuncil stating that the works were not going to be completed before your potential sublet this might be an easier case to run.
However in reality I guess the amount of money involved is relatively minor and not worth pursuing. Another approach is to suggest to the Council that the property was vacant from 1 Nov to date when works started, and then occupied during the works, and then empty once the works were completed. Giving you a three month exemption at the end of the works.
brynmaxwell said:
davidjpowell
As you gather from communications below relationship with tenant was not a happy one and even return of keys was problematical. But my agent received keys back on 28 Nov but keys were GIVEN BACK to council to carry out works, although we could still gain access carry out viewings.
27 Nov - Email to me from my surveyor
Council surveyor is concerned that if the keys are not with us before 30th Nov then we will say that they haven't vacated the premises and must continue for a further 3 months (periodic tenancy). Likewise, I've told him that with the attitude of the Council's solicitors over matters, they may try to argue that there are other implications as we've taken the keys back early.
To get round this, can you please provide me with a letter that I can email to surveyor confirming that if they give us the keys tomorrow afternoon then we will not pursue them for a continuation tenancy from 1st December.
In the meantime, I trust you will appreciate my concerns about taking keys back early given the Council's solicitors approach to matters in the past. I think there is a degree of mistrust on both sides.
(I don't think I picked up email in time to provide assurance I would not pursue continuation tenancy.)
28 Nov Email from my surveyor to council surveyor
Whilst I am awaiting my client to come back to me, could I equally suggest that you/the Council provide us with a letter confirming that if we do accept keys from you today then this will not be deemed as an early surrender of the lease and that all provisions & covenants, etc within the existing lease will continue until the time of contractual expiry. If I have this then I would be happy to take keys back from you, strictly on the basis that I am holding them as agent and am not accepting them in consideration of an early surrender of the lease.
I'm a bit confused re the Periodic Tenancy. Normally if the tenant does not provide vacant possession by the due date then the break fails so of it is a lease it continues to run. Was the lease due to expire and the council simply giving notice? I'm surprised the a Local Authority could be so pro-active as to implement a break.As you gather from communications below relationship with tenant was not a happy one and even return of keys was problematical. But my agent received keys back on 28 Nov but keys were GIVEN BACK to council to carry out works, although we could still gain access carry out viewings.
27 Nov - Email to me from my surveyor
Council surveyor is concerned that if the keys are not with us before 30th Nov then we will say that they haven't vacated the premises and must continue for a further 3 months (periodic tenancy). Likewise, I've told him that with the attitude of the Council's solicitors over matters, they may try to argue that there are other implications as we've taken the keys back early.
To get round this, can you please provide me with a letter that I can email to surveyor confirming that if they give us the keys tomorrow afternoon then we will not pursue them for a continuation tenancy from 1st December.
In the meantime, I trust you will appreciate my concerns about taking keys back early given the Council's solicitors approach to matters in the past. I think there is a degree of mistrust on both sides.
(I don't think I picked up email in time to provide assurance I would not pursue continuation tenancy.)
28 Nov Email from my surveyor to council surveyor
Whilst I am awaiting my client to come back to me, could I equally suggest that you/the Council provide us with a letter confirming that if we do accept keys from you today then this will not be deemed as an early surrender of the lease and that all provisions & covenants, etc within the existing lease will continue until the time of contractual expiry. If I have this then I would be happy to take keys back from you, strictly on the basis that I am holding them as agent and am not accepting them in consideration of an early surrender of the lease.
Chris's idea of occupying during the works (assuming they were done on one go and not spread over the weeks is a good one), and would help reduce the rate burden. What is the RV here - is the bill thousands or hundreds? - it probably makes a difference in terms of running an argument.
gtr-gaz said:
Sorry, can't help with the points you have raised, just curious to know why the delaps scedule was not drawn up until after the vacation date?
Normally these are carried out weeks before to ensure they are completed by the tenant before keys are handed back.
Latest Code of Practice says that dilaps schedule should be served no later than 56 days after the termination of the lease. It's a bit of a trap with breaks really.Normally these are carried out weeks before to ensure they are completed by the tenant before keys are handed back.
Edited by davidjpowell on Saturday 5th December 09:06
To further confuse matters, council rented a shop and office behind, but originally under two separate leases. On an earlier renewal council insisted on combining the two under one lease. So I have situation where dilaps is for 2 properties combined, but each is separately rated.
Rates dispute applies to the office only, as I paid the arrears on the shop in with rate demand for 2009/10. The disputed amount is small – only £200, but were I successful in establishing council was liable for the disputed 30 days, it could then be argued council was also liable for rates on the shop from expiry of lease (30 Nov) until works were completed 1st week of April. Then it’s a whole different ball game – 4 months @ £1,900 + 3 months void rates exemption commencing 1 April – total value £13,300. (Exemption was applied from 30 Nov, making me liable from 1 March.)
Council’s cash settlement offer for the two premises combined was £10,000, but surveyor wanted £10,000 + VAT (property is not VAT registered). Council refused, so undertook works itself.
Potential let was only for few days (an exhibition). Nonetheless, it was a lost because council contractors were working in the premises at the time. I don’t know why dilaps schedule wasn’t drawn up before break was exercised (it was a break, not lease expiry).
To recap, redecoration had been done by 28 Nov (lease ended 30 Nov), but inspection on 1 Dec revealed number of relatively minor snags (cabling not removed etc) that shouldn’t have taken 4 months to complete. My argument all along has been council was effectively in occupation, because keys were not finally handed back until April. But council says no, premises could be viewed, so I was in beneficial occupation.
I seem to have reached an impasse – hence my wanting matter referred back to court. But the court says case has nothing to do with them – the council hold all papers relating to rate summonses, so has no involvement !!!!!!
Thanks for all the input.
Rates dispute applies to the office only, as I paid the arrears on the shop in with rate demand for 2009/10. The disputed amount is small – only £200, but were I successful in establishing council was liable for the disputed 30 days, it could then be argued council was also liable for rates on the shop from expiry of lease (30 Nov) until works were completed 1st week of April. Then it’s a whole different ball game – 4 months @ £1,900 + 3 months void rates exemption commencing 1 April – total value £13,300. (Exemption was applied from 30 Nov, making me liable from 1 March.)
Council’s cash settlement offer for the two premises combined was £10,000, but surveyor wanted £10,000 + VAT (property is not VAT registered). Council refused, so undertook works itself.
Potential let was only for few days (an exhibition). Nonetheless, it was a lost because council contractors were working in the premises at the time. I don’t know why dilaps schedule wasn’t drawn up before break was exercised (it was a break, not lease expiry).
To recap, redecoration had been done by 28 Nov (lease ended 30 Nov), but inspection on 1 Dec revealed number of relatively minor snags (cabling not removed etc) that shouldn’t have taken 4 months to complete. My argument all along has been council was effectively in occupation, because keys were not finally handed back until April. But council says no, premises could be viewed, so I was in beneficial occupation.
I seem to have reached an impasse – hence my wanting matter referred back to court. But the court says case has nothing to do with them – the council hold all papers relating to rate summonses, so has no involvement !!!!!!
Thanks for all the input.
David, I don’t appear to have lease – only draft, which does not include breakclause (added later). From memory, this was lease renewal that council had been dragging its feet on since 2005 and didn’t sign until 2008. No sooner was ink dry council triggered break, so I suspect my solicitors never got round to sending engrossment. I only have Notice to Terminate doc.
Sorry I can’t be more helpful
Sorry I can’t be more helpful
I am not sure I agree with the Council necessarially. The situation is that under most leases they should have completed the delapidation works by the end of the lease (irrespective of whether it was a break clause, or the end of the lease). If the works were not completed then they have no choice but to pay the Landlord to do them as they don't have access to the property. It seems to me that the OP has been badly advised.
I think an argument could be made that the Council were in occupation of the property as you could seek to argue that they were in beneficial occupation as doing the works after the lease expired enabled them to avoid the higher charge the Landlords workers would have charged.
I think though you have an opportunity though to play around with the rating assessments to save money. If the Council occupied the shop and office where they contiguos? ie can you put a fence around them which would circle them both without crossing public highways etc? If so then as the properties were in a single occupation then they would a single assessment. You can make a proposal to merge properties at anytime upto 31 March 2010 and backdate the merger to the day of the event or 1 April 2005 whichever is later. In theory this would give a lower total rates bill as you'd want an allowance fo the combination of the properties. but the advantage would be that after the Council vacated you did of course market the property as a single unit. However after 3 months you decided to market them seperately. You therefore ask the VO to split the properties from 1 March, and with any luck that will reset the empty rates clock again. Whether it does or not depends on the Councils policy.
You might also want to ask your surveyor and lawyer why they believe the Break clause was validilly operated when the delpas works were not completed!
You might also want to check on what address the summons for non-payment of rates was served. I believe if the property was owned by a company it should be sent to te companies registered office, but would need to check that out further.
I think an argument could be made that the Council were in occupation of the property as you could seek to argue that they were in beneficial occupation as doing the works after the lease expired enabled them to avoid the higher charge the Landlords workers would have charged.
I think though you have an opportunity though to play around with the rating assessments to save money. If the Council occupied the shop and office where they contiguos? ie can you put a fence around them which would circle them both without crossing public highways etc? If so then as the properties were in a single occupation then they would a single assessment. You can make a proposal to merge properties at anytime upto 31 March 2010 and backdate the merger to the day of the event or 1 April 2005 whichever is later. In theory this would give a lower total rates bill as you'd want an allowance fo the combination of the properties. but the advantage would be that after the Council vacated you did of course market the property as a single unit. However after 3 months you decided to market them seperately. You therefore ask the VO to split the properties from 1 March, and with any luck that will reset the empty rates clock again. Whether it does or not depends on the Councils policy.
You might also want to ask your surveyor and lawyer why they believe the Break clause was validilly operated when the delpas works were not completed!
You might also want to check on what address the summons for non-payment of rates was served. I believe if the property was owned by a company it should be sent to te companies registered office, but would need to check that out further.
Part of me wonders whether the break clause could have been invalid because of the dilapidation works, but given that you have accepted the dilapidation works there is probably no mileage in that anyway.
If the office and shop are contiguous then to me it sounds like the assessments are incorrect and should be merged into one. You would be able to have this backdated to the date the council took occupation (or 1 April 2005 if earlier), and it should result in a smaller overall assessment so result in a saving.
If you can argue that the council did have occupation that would be good, but if they were not paying rent, not in actual possession other than holding keys to do works I think ultimately its not an argument you can win, especially when even though they are different departments they are in the same authority.
Chris talks about taking it out of the rating list for the period of the works. I'm not as involved as I used to be, but it used to the case that to stand any chance of achieving this you had to make the proposal as the start of the works.
Edit = I see Chris has also had simlar thoughts
I believe the period you had to occupy before being able to claim the rate exemption is 6 weeks - hopefully Chris will be able to confirm. There are companies that claim to help reduce the overhead of empty rates. How legal they are I'm not sure.
If the office and shop are contiguous then to me it sounds like the assessments are incorrect and should be merged into one. You would be able to have this backdated to the date the council took occupation (or 1 April 2005 if earlier), and it should result in a smaller overall assessment so result in a saving.
If you can argue that the council did have occupation that would be good, but if they were not paying rent, not in actual possession other than holding keys to do works I think ultimately its not an argument you can win, especially when even though they are different departments they are in the same authority.
Chris talks about taking it out of the rating list for the period of the works. I'm not as involved as I used to be, but it used to the case that to stand any chance of achieving this you had to make the proposal as the start of the works.
Edit = I see Chris has also had simlar thoughts
I believe the period you had to occupy before being able to claim the rate exemption is 6 weeks - hopefully Chris will be able to confirm. There are companies that claim to help reduce the overhead of empty rates. How legal they are I'm not sure.
Edited by davidjpowell on Saturday 5th December 17:32
You can serve a proposal to delete at any time becase the "material day" is the day of the event ie the day it became incapable of occupation. If he was seeking a reduction in the assessment for the period of the works (ie an allowance rather than deletion)then yes the proposal would have needed to be served during the works and ideally on the first day of the works. It is commonly where people get caught out, a public utilty starts highly disruptive roadworks to replace a sewer, gaspie or whatever. Ratepayed complains to utility who say we're only here for 10 weeks. After 12 weeks the ratepayer has another word with the utility and gets told we hit problems we'll be another 4 weeks. After 16 weeks the ratepayer has had enough and phones the Council who say speak to VO. Ratepayer speaks to the VO who senda proposal form. Ratepayer completes it and returns it in Week 18. In week 25 the works finish. 9 months later the VO contacts the ratepayer and states that whem you appealled the works only had 7 weeks to run and therefore no allowance was warrented. You should have appealled in week 1 and you might have got something. Indeed there have been occasions whenneighbouring properties have been affected by the same works. One appealled at the beginning of the works and gets a reduction. The other appealled 3 months later and gets told the works were nearly finished so no reduction!
Incidentially telling David this is preaching to the converted!
Incidentially telling David this is preaching to the converted!
Thank you Chris & David you insight is invaluable, although I suspect the opportunity to put them into practice might have passed with passage of time!
The properties were contiguous, so in theory I could request reassessment back to 2005. But would not backdating to 2005 benefit the tenant rather than me, as council would get any refund to December 08, with only the balance being due to me from December? (Although I can see there is the possibility for me to get two 3-month exemptions.) Would the fact I secured a new shop tenant as of 29 September preclude me from applying for reassessment – it would mean getting the two premises combined until Sept 09 then reassessed as separate unit from September?
In view of what council said in recent letter: -
“Once the lease has expired council had relinquished its’ obligation to occupy the property and for rating purposes the landlord is then responsible for premises. The additional works that the council undertook did not make the council legally responsible for the rates, and it could not reoccupy the premises again after the end of the lease.”
If I’ve understood correctly what you both are saying, it sounds like there’s little point continuing to argue council was in possession – they say “No” and that’s an end to it – correct?
Although Chris you are saying: -
"I think an argument could be made that the Council were in occupation of the property as you could seek to argue that they were in beneficial occupation as doing the works after the lease expired enabled them to avoid the higher charge the Landlords workers would have charged."
I thought our illustrious leader G.B. stopped the policy of exempting from rates property while they were being refurbished when he doubled the rates payable on void premises from April 2009?
The properties were contiguous, so in theory I could request reassessment back to 2005. But would not backdating to 2005 benefit the tenant rather than me, as council would get any refund to December 08, with only the balance being due to me from December? (Although I can see there is the possibility for me to get two 3-month exemptions.) Would the fact I secured a new shop tenant as of 29 September preclude me from applying for reassessment – it would mean getting the two premises combined until Sept 09 then reassessed as separate unit from September?
In view of what council said in recent letter: -
“Once the lease has expired council had relinquished its’ obligation to occupy the property and for rating purposes the landlord is then responsible for premises. The additional works that the council undertook did not make the council legally responsible for the rates, and it could not reoccupy the premises again after the end of the lease.”
If I’ve understood correctly what you both are saying, it sounds like there’s little point continuing to argue council was in possession – they say “No” and that’s an end to it – correct?
Although Chris you are saying: -
"I think an argument could be made that the Council were in occupation of the property as you could seek to argue that they were in beneficial occupation as doing the works after the lease expired enabled them to avoid the higher charge the Landlords workers would have charged."
I thought our illustrious leader G.B. stopped the policy of exempting from rates property while they were being refurbished when he doubled the rates payable on void premises from April 2009?
On an interesting aside, the rates burden is passed on to the 'beneficial' occupier, therefore in the case of a tenant holding over to undertake repairs, but where a lease has been formally determined then the 'beneficial' occupier is likely to be construed to be the landlord.
Having looked through this I would be agreeing with Chris and David and looking very closely at whether the break had been validly served - reading the above I suspect not through non compliance with their repairing convenants, but your agent may have shown negligence in accepting the keys for the property (and thus indicating the end of the tenancy) knowing of the properties poor state of repair.
Having looked through this I would be agreeing with Chris and David and looking very closely at whether the break had been validly served - reading the above I suspect not through non compliance with their repairing convenants, but your agent may have shown negligence in accepting the keys for the property (and thus indicating the end of the tenancy) knowing of the properties poor state of repair.
It would seem general consensus is surveyor was at fault accepting keys back, so little mileage in pursuing matter further.
Pity, as I have had a good relationship with firm for many years.
What about suggestion I should ask V.O. to combine two premises and back date to 2005. Can it stll be done even though shop has since been let?
P.S Probably backing a loser again, but I will be posting question regarding another battle I’m embroiled in with same tenant (council) over rubbish discovered behind sealed doorway in basement.
Any input would be much appreciated.
Pity, as I have had a good relationship with firm for many years.
What about suggestion I should ask V.O. to combine two premises and back date to 2005. Can it stll be done even though shop has since been let?
P.S Probably backing a loser again, but I will be posting question regarding another battle I’m embroiled in with same tenant (council) over rubbish discovered behind sealed doorway in basement.
Any input would be much appreciated.
brynmaxwell said:
It would seem general consensus is surveyor was at fault accepting keys back, so little mileage in pursuing matter further.
Pity, as I have had a good relationship with firm for many years.
What about suggestion I should ask V.O. to combine two premises and back date to 2005. Can it stll be done even though shop has since been let?
P.S Probably backing a loser again, but I will be posting question regarding another battle I’m embroiled in with same tenant (council) over rubbish discovered behind sealed doorway in basement.
Any input would be much appreciated.
It does, sadly, seem as though your advice may have been poor here. If you have suffered a material loss as a consequence of this then you ought probably to consider taking action against whoever gave you that advice (whichever advisor it was).Pity, as I have had a good relationship with firm for many years.
What about suggestion I should ask V.O. to combine two premises and back date to 2005. Can it stll be done even though shop has since been let?
P.S Probably backing a loser again, but I will be posting question regarding another battle I’m embroiled in with same tenant (council) over rubbish discovered behind sealed doorway in basement.
Any input would be much appreciated.
As it turned out I should imagine that the council (as tenant) were jumping for joy - effectively they had nearly 5 months of rent-free time in which to attend to a few jobs (which could therefore be used as infill amongst other more pressing tasks). I've never known a tenant given such latitude after surrender of the property!
Any how, I'd look seriously at the break issue if you want recompense.
Yes you can apply for a back-dated merger even though the shop part has subsequent;y been let. In fact it arguably helps your case on the subsequent split as it proves you were marketing the two seperately!
So basically you want a merger from 1 April 2005 to a relevant date after the property was vacated. When you will want to split again. The intention is to maximise the empty rates exetpion rather than save mony on the day to day payments although that will be a side effect.
The issue on the empty rates is more complex as historically buildings undergoing works have been considered vacant. Therefore even if you persuade the COuncil they were liable for the rates during the works they would just deduct it from the empty rates period so you would remian in the same position. Depending on the lease terms (if it excludes the tenant using the empty rates provision at the end of the lease) you could then argue that the Council had been able to stay in occupation as they had not done the work they should have done, and therefore they should pay for the period of the works as they were in beneficial occupation.
However I suspect the only remedy is a letter to the senior partner of your surveyor and lawyer asking why they accepted the break clause had been activated when the Council then required 4 months to do the necessary works. You could make it a formal complaint and use their complaints procedure and ask for the compensation you believe is reasonable. You might find they are willing to compensate you to avoid a complaint to their professional body or an insurance claim!
So basically you want a merger from 1 April 2005 to a relevant date after the property was vacated. When you will want to split again. The intention is to maximise the empty rates exetpion rather than save mony on the day to day payments although that will be a side effect.
The issue on the empty rates is more complex as historically buildings undergoing works have been considered vacant. Therefore even if you persuade the COuncil they were liable for the rates during the works they would just deduct it from the empty rates period so you would remian in the same position. Depending on the lease terms (if it excludes the tenant using the empty rates provision at the end of the lease) you could then argue that the Council had been able to stay in occupation as they had not done the work they should have done, and therefore they should pay for the period of the works as they were in beneficial occupation.
However I suspect the only remedy is a letter to the senior partner of your surveyor and lawyer asking why they accepted the break clause had been activated when the Council then required 4 months to do the necessary works. You could make it a formal complaint and use their complaints procedure and ask for the compensation you believe is reasonable. You might find they are willing to compensate you to avoid a complaint to their professional body or an insurance claim!