Anybody know of any cheap (freeware) software to do this:-

8:15am -> 12:15pm
1pm->4:15pm


Total=7 hours. 15 Mins.

Its ok for 3 or 4 amounts but having a page full is giving me a headache.

randlemarcus

13,646 posts

261 months

Tuesday 27th June 2006
quotequote all
Excel? Word might also be able to calculate it..
I know its not freeware, but its fairly ubiquitous.

scared but happy

Original Poster:

24,147 posts

259 months

Tuesday 27th June 2006
quotequote all
Any ideas how? If so I will use Openoffice.

Scraggles

7,619 posts

254 months

Tuesday 27th June 2006
quotequote all
not quite sure what u want or are trying to put across

this is a column from spreadsheet

8.00 site 1
8.30 site 2
9.00 etc
9.30 zzz

You can change it to whatever time period you want and then add in what u have been doing

twister

1,592 posts

266 months

Tuesday 27th June 2006
quotequote all
In Excel:

Select columns A-C and set the cell format to Time
In cell C1, enter the formula "=B1-A1"
Copy this formula (with the Fill Down command) into as many rows as you need
In cell D1, enter the formula "=SUM(C:C)"
Enter your start times in column A and your finish times in column B...

Note: this won't work if your start-finish timepair spans midnight (e.g. 23:00 -> 01:15).


Edited by twister on Tuesday 27th June 18:21

iaint

10,040 posts

268 months

Tuesday 27th June 2006
quotequote all
twister said:
In Excel:

Select columns A-C and set the cell format to Time
In cell C1, enter the formula "=B1-A1"
Copy this formula (with the Fill Down command) into as many rows as you need
In cell D1, enter the formula "=SUM(C:C)"
Enter your start times in column A and your finish times in column B...



Remember to add a column to put in how long you have for lunch and sub it from teh total. Then have fun converting from the hours format back to normal numbers for weekly totals...

twister

1,592 posts

266 months

Tuesday 27th June 2006
quotequote all
iaint said:
Remember to add a column to put in how long you have for lunch and sub it from teh total.


I was assuming the OP was explicitly entering just the hours worked - hence their example start-finish pairs having a gap which looks suspiciously like a lunchbreak.

iaint said:
Then have fun converting from the hours format back to normal numbers for weekly totals...


Yeah, just remembered that...

twister

1,592 posts

266 months

Tuesday 27th June 2006
quotequote all
Hmm, second attempt...

Select columns A-C and set the cell format to Time
In cell C1, enter the formula "=IF(B1>=A1,B1-A1,B1-A1+1)"
Copy this formula (with the Fill Down command) into as many rows as you need
In cell D1, enter the formula "=SUM(C:C)"
Set D1 cell format to Time, selecting the type which doesn't restrict the hours value to 23 (in Excel 2000 it's the 6th type listed
Enter your start times in column A and your finish times in column B...


This will now permit timepairs to span midnight (though the maximum length of each timepair is still limited to 23h59m), and the overall total shown will be correct for values of 24 hours or more.


The .xls version of this can be found here

scared but happy

Original Poster:

24,147 posts

259 months

Tuesday 27th June 2006
quotequote all
That is EXACTLY what I am looking for. With a bit of table fidding it has saved me loads of time.

Thank you very much.


Edited by scared but happy on Tuesday 27th June 21:32