Hi doing college project on microsoft project and when i am changeing the working time the hour will not change from 08:00 to 12:00 then hour for dinner 13:00 to 17:00 but i want to finish at 16:00 i have change the total hours in the week to 35 from 40 and 7 hours a day but still will not chnge these times any help is grateful thanks ross
when changing the working time be careful to always change in two locations:
Tools/Change working time
AND
Tools/Options/Caladar
Otherwise you'll end up with some very odd effects.
HTH
Miles
PS what's the project and is there anything else you need help with, MPS is one of my core tools for my sins
Tools/Change working time
AND
Tools/Options/Caladar
Otherwise you'll end up with some very odd effects.
HTH
Miles
PS what's the project and is there anything else you need help with, MPS is one of my core tools for my sins
Thanks mile stylus changed the time on both. The project is about manufacturing wheel barrows and one problem i have is that the foreman looks after 20 operators and therefore by my calculations is equal to 5% per operator so on a task of 100 man hours the foreman is assigned to this it would equal to 5 hours but when another operator is asssigned it reduces the task down to 50 does the foremans time still stay at 5 hours which would need to be 10% or does it reduce to 2.5 hours which is 5% of the new duration when two operators do the task. thanks ross