Microsoft project 2003
Author
Discussion

Ross_328i_sport

Original Poster:

317 posts

241 months

Monday 18th December 2006
quotequote all
Hi doing college project on microsoft project and when i am changeing the working time the hour will not change from 08:00 to 12:00 then hour for dinner 13:00 to 17:00 but i want to finish at 16:00 i have change the total hours in the week to 35 from 40 and 7 hours a day but still will not chnge these times any help is grateful thanks ross

hornie

368 posts

272 months

Tuesday 19th December 2006
quotequote all
Tools>Options from teh drop down menu - click on teh calenmder tab - you shoudl eb able to set your stuff there

Ross_328i_sport

Original Poster:

317 posts

241 months

Tuesday 19th December 2006
quotequote all
cheers thanks very much

Ross

Miles_stylus

332 posts

262 months

Wednesday 20th December 2006
quotequote all
when changing the working time be careful to always change in two locations:

Tools/Change working time
AND
Tools/Options/Caladar

Otherwise you'll end up with some very odd effects.

HTH

Miles
PS what's the project and is there anything else you need help with, MPS is one of my core tools for my sins

Ross_328i_sport

Original Poster:

317 posts

241 months

Wednesday 20th December 2006
quotequote all
Thanks mile stylus changed the time on both. The project is about manufacturing wheel barrows and one problem i have is that the foreman looks after 20 operators and therefore by my calculations is equal to 5% per operator so on a task of 100 man hours the foreman is assigned to this it would equal to 5 hours but when another operator is asssigned it reduces the task down to 50 does the foremans time still stay at 5 hours which would need to be 10% or does it reduce to 2.5 hours which is 5% of the new duration when two operators do the task. thanks ross