Concreting Strip Foundations - How Long Does It Take ?
Discussion
I want to pour approx 500mm deep concrete in 75 linear metres of 0.6m wide foundations.
The layout is a rectangle with 2 bays and 2 dividing walls front to back and side to side.
The inspector will hopefully pass them today at 10.30am.
Is it realistic that 2 men can get approx 22m3 in and level starting at 11am in a day ?
Both of us have done similar before BUT many years ago and we weren't in charge then.
Cheers
The layout is a rectangle with 2 bays and 2 dividing walls front to back and side to side.
The inspector will hopefully pass them today at 10.30am.
Is it realistic that 2 men can get approx 22m3 in and level starting at 11am in a day ?
Both of us have done similar before BUT many years ago and we weren't in charge then.
Cheers
Should anyone need to know in the future...
It was a fairly easy.
I ended up using 33m3 placing it approx 600mm deep and 3 of us did it 8.30 - 4.30
Unfortunately we only had one waggon of turn around (just over an hour) and ideally we could have done with the first 3 almost simultaneously.
It was a fairly easy.
I ended up using 33m3 placing it approx 600mm deep and 3 of us did it 8.30 - 4.30
Unfortunately we only had one waggon of turn around (just over an hour) and ideally we could have done with the first 3 almost simultaneously.