Concreting Strip Foundations - How Long Does It Take ?
Concreting Strip Foundations - How Long Does It Take ?
Author
Discussion

redgriff500

Original Poster:

28,982 posts

287 months

Tuesday 11th October 2011
quotequote all
I want to pour approx 500mm deep concrete in 75 linear metres of 0.6m wide foundations.

The layout is a rectangle with 2 bays and 2 dividing walls front to back and side to side.

The inspector will hopefully pass them today at 10.30am.

Is it realistic that 2 men can get approx 22m3 in and level starting at 11am in a day ?

Both of us have done similar before BUT many years ago and we weren't in charge then.

Cheers

pimpin gimp

3,318 posts

224 months

Tuesday 11th October 2011
quotequote all
How big are the concrete wagons? Presuming 6 or 8m^3 that's only 3 or 4 loads, shouldn't be an problem to get it laid. Presume you've ordered them to arrive in quick succession?

redgriff500

Original Poster:

28,982 posts

287 months

Tuesday 11th October 2011
quotequote all
6m3 loads.

I daren't order until the founds are passed.


dickymint

28,553 posts

282 months

Tuesday 11th October 2011
quotequote all
Don't forget the clocks go back soon. I think one short day will be pushing it. Maybe get it pumped in to save time on spreading?

redgriff500

Original Poster:

28,982 posts

287 months

Friday 14th October 2011
quotequote all
Should anyone need to know in the future...

It was a fairly easy.

I ended up using 33m3 placing it approx 600mm deep and 3 of us did it 8.30 - 4.30

Unfortunately we only had one waggon of turn around (just over an hour) and ideally we could have done with the first 3 almost simultaneously.



Edited by redgriff500 on Friday 14th October 10:07