Concrete slab and poker.
Author
Discussion

Harpo

Original Poster:

482 posts

213 months

Tuesday 15th November 2011
quotequote all
Not playing cards outside in the Autumn gloom!
I'm doing a workshop extension to my garage and have finished the shuttering and hardcore.
Concrete booked for Thursday am.
I am hiring a vibrating poker to get the air out and would appreciate some help from those in the know as I haven't used one before.
Will this poker give a good smooth finish (with a sloppy mix) or do I still need to float it off?
Also, do I need to buy wellies to deal with the centre part as it can't be reached from the sides (6.2 metres by 4 metres) or will the poker sort that out for me? TIA guys.

jas xjr

11,309 posts

270 months

Tuesday 15th November 2011
quotequote all
Poker will get the air out no problems. But you will still need to trowel the slab off.
Get some wellies anyway , you can hose them off at the end of your day.

C Lee Farquar

4,243 posts

247 months

Tuesday 15th November 2011
quotequote all
Don't have it too wet if you're using a poker, some water will separate and float on the surface.

dickymint

29,266 posts

289 months

Tuesday 15th November 2011
quotequote all
Why are you using a poker on a slab? Only ever used one on something like really deep shuttering.

Spudler

3,985 posts

227 months

Tuesday 15th November 2011
quotequote all
For the job in question i wouldn't bother using a poker.
Ask for a "garage floor mix" (10mm stone) which is far easier to get a decent finish.

Harpo

Original Poster:

482 posts

213 months

Friday 18th November 2011
quotequote all
Thanks for the input guys.
I got myself in a tizz as I was reading conflicting information on various sites. I was surprised at the depth of the subject on laying concrete. It gets really technical!
Anyway, in the end I didn't get the poker. As advised, 100 mill doesn't need it.
Had 4 of us on the job and needed everyone for certain! 2 with wellies on, spreading with a rake and shovel, whilst 2 did the old sawing and tamping using a 4.5 metre baton.
To get a good finish, I hired a Glider Trowel (Uncle Sam term Fresno?) without which the finish would be dire. With, its like a billiard table. It was great to see the finish improve with each stroke.
B and Q sell tons of sand and cement a day at the local mega store but don't sell the tools to work it.
No edging tools, only available on 24 hour order. WTF! I needed it that day!
Local builders shop had one there. £36 ...... ouch but got 10% knocked off. Even so, a tad expensive. Anyway, the trowel was worth the money so the edges have been arrissed to avoid spalling in the future. Ooow, hark at me coming out with all the jargon!
Anyway, should I move house, the next slab will be done by a contractor and I'll be down the pub.
Never again, too much like hard work.

dickymint

29,266 posts

289 months

Friday 18th November 2011
quotequote all
Harpo said:
Thanks for the input guys.
I got myself in a tizz as I was reading conflicting information on various sites. I was surprised at the depth of the subject on laying concrete. It gets really technical!
Anyway, in the end I didn't get the poker. As advised, 100 mill doesn't need it.
Had 4 of us on the job and needed everyone for certain! 2 with wellies on, spreading with a rake and shovel, whilst 2 did the old sawing and tamping using a 4.5 metre baton.
To get a good finish, I hired a Glider Trowel (Uncle Sam term Fresno?) without which the finish would be dire. With, its like a billiard table. It was great to see the finish improve with each stroke.
B and Q sell tons of sand and cement a day at the local mega store but don't sell the tools to work it.
No edging tools, only available on 24 hour order. WTF! I needed it that day!
Local builders shop had one there. £36 ...... ouch but got 10% knocked off. Even so, a tad expensive. Anyway, the trowel was worth the money so the edges have been arrissed to avoid spalling in the future. Ooow, hark at me coming out with all the jargon!
Anyway, should I move house, the next slab will be done by a contractor and I'll be down the pub.
Never again, too much like hard work.
Nice, well done. Next time mix the compo yourself you wimp!!

Harpo

Original Poster:

482 posts

213 months

Friday 18th November 2011
quotequote all
3.1 tons with my tennis elbow? hehe
I worked it out as about 2.5. I got the extra .6 for just £30. That's was a bargin!
It would build up the muscles eh?

MATTP77

697 posts

226 months

Wednesday 23rd November 2011
quotequote all
Spudler said:
For the job in question i wouldn't bother using a poker.
Ask for a "garage floor mix" (10mm stone) which is far easier to get a decent finish.
Begs the question, why are you using a poker for a finish, they serve only one purpose...!

MATTP77

697 posts

226 months

Wednesday 23rd November 2011
quotequote all
Harpo said:
Also, do I need to buy wellies to deal with the centre part as it can't be reached from the sides.
scratchchin

dickymint

29,266 posts

289 months

Wednesday 23rd November 2011
quotequote all
MATTP77 said:
Spudler said:
For the job in question i wouldn't bother using a poker.
Ask for a "garage floor mix" (10mm stone) which is far easier to get a decent finish.
Begs the question, why are you using a poker for a finish, they serve only one purpose...!