I have a slight problem and I am hoping the PH massive can help?

Building Control has requested a Part P for the electrical work carried out, but only on the shower which is actually thermostatic was have gone back to this on that point. But now they are trying to add after inspection for the Part P for the whole En suite. Unfortunately my builder is now undergoing cancer treatment and has moved, so is really not in a good way to sort the paperwork out for me.

Should I tell this to building control and try to show the human side of this situation, or will telling them make it worst.

i.e. I will then have to find someone to remove walls and certify it at additional expensive?

Brite spark

2,108 posts

232 months

Monday 21st November 2011
quotequote all
I assume electrical work has been carried out in the ensuite? Not completely clear.

A periodic inspection report should suffice for building control if you can't get the builder to sort it, Walls would not need to be stripped back as this will be noted as unable to inspect on cert

caz_manc

Original Poster:

525 posts

226 months

Monday 21st November 2011
quotequote all
They have already inspected.

The problem is the person who inspected is now on long term sick. Someone else had to be asked the question about that it was a thermostatic shower and therefore not electric and therefore does not need the cert.

You said there is an issue if there are unable to verify electric. This might be the case with mine, as I was not told that I needed an inspection during the work. So all the work was done before the inspection.

Should I tell them about the builders health?

Or do I have a case to say that as the Part P for the whole en-suite was not brought up in the inspection, it should not be requested now?

Brite spark

2,108 posts

232 months

Monday 21st November 2011
quotequote all
caz_manc said:
They have already inspected.
The problem is the person who inspected is now on long term sick. Someone else had to be asked the question about that it was a thermostatic shower and therefore not electric and therefore does not need the cert.
no electric work - no part p as far as i am aware.
Unless the bco believe you have carried out electrical work in the room and want paperwork to that effect.
If the company was not a one man band they should have procedures to solve this.


caz_manc said:
You said there is an issue if there are unable to verify electric.
certain things would be impractical to check if a pir was used instead of eic, hence there are allowances for this in the pir

caz_manc said:
Should I tell them about the builders health?

Or do I have a case to say that as the Part P for the whole en-suite was not brought up in the inspection, it should not be requested now?
Speak to building control they should be able to tell you what they want, why and how you can achieve that, just. Explain the situation with the builder

jason s4

16,810 posts

201 months

Monday 21st November 2011
quotequote all
ANY electrical work in a 'special location' (eg bathroom, kitchen etc), will require an electrical installation certificate and be notified to your LABC.

By the sounds of it, the builder did the work, but could not notify as he isnt registered with a competent persons scheme.

You MIGHT get away with a third party inspection, but at the end of the day, the LABC will have the final say, and you will just have to do what they want.

Basically ALWAYS use a registered electrician, even if the builder says he "can do the work".

caz_manc

Original Poster:

525 posts

226 months

Monday 21st November 2011
quotequote all
He has been registeted in the past. But it would be in his ex partners place. And it expired in august. He did the work in Jan. He is too ill now to do the test, to get recertified.

Obviously I don't know now if the cert is true. But he was an excellent builder and I have seen him after the split and at the point he found out about the cancer. e

jason s4

16,810 posts

201 months

Monday 21st November 2011
quotequote all
That may well be and im sorry to hear of his illness, however, you are still in the position of having works not signed off correctly and could affect the sale of your home in the future.

Firstly, I suggest you contact your LABC and explain the situation fully.