Hi bit of infomation needed please guys.

I'm in the process of renovating my bathroom and have had the walls skimmed.

Now looking at having the walls tiled with 12mm stone (Heavy!!).

How long will I need to leave between skim and stone?

Any info would be cool

Cheers

Stu R

21,707 posts

246 months

Thursday 1st December 2011
quotequote all
Ours went on after 48 hours, still standing 6 months later.

Spudler

3,985 posts

227 months

Thursday 1st December 2011
quotequote all
I hope the wall will take that kind of tile.
If its just skimmed then a few days it will be dry, you'll soon tell.
Even if the adhesive says non-primer i suggest still primimg with something like http://www.tileadhesive.co.uk/acrilic-bonding.html

Hoonabator

Original Poster:

604 posts

257 months

Thursday 1st December 2011
quotequote all
Cheers guys, seems nothing to worry about then.

dickymint

29,278 posts

289 months

Friday 2nd December 2011
quotequote all
Plaster is NOT a suitable substrate for fixing 12mm stone to. You may get away with it you may not. You should have saved the time and money by fixing directly onto bare plasterboard.

Trust me the Missus works here..............

http://www.mandarinstone.com/fixing_sealing

Simpo Two

93,179 posts

296 months

Friday 2nd December 2011
quotequote all
dickymint said:
Plaster is NOT a suitable substrate for fixing 12mm stone to. You may get away with it you may not. You should have saved the time and money by fixing directly onto bare plasterboard.
But are they plasterboard or block walls?

I had both when doing my bathroom (12mm stone); blockwork was skimmed and plasterboard primed directly. I was careful to do it by the book and use the recommended primer and adhesive. IIRC the weight is about 22kg/m2 and I didn't want that falling on me! Six years on and it's fine.

dickymint

29,278 posts

289 months

Friday 2nd December 2011
quotequote all
Simpo Two said:
dickymint said:
Plaster is NOT a suitable substrate for fixing 12mm stone to. You may get away with it you may not. You should have saved the time and money by fixing directly onto bare plasterboard.
But are they plasterboard or block walls?

I had both when doing my bathroom (12mm stone); blockwork was skimmed and plasterboard primed directly. I was careful to do it by the book and use the recommended primer and adhesive. IIRC the weight is about 22kg/m2 and I didn't want that falling on me! Six years on and it's fine.
Correct assuming your blockwork was skimmed with cement render and not Gypsum Plaster.

Simpo Two

93,179 posts

296 months

Friday 2nd December 2011
quotequote all
dickymint said:
Correct assuming your blockwork was skimmed with cement render and not Gypsum Plaster.
Hmm, having checked the photos it's the slightly pink stuff which I deduce is wrong... and the guy knew what I was going to tile with. On one side I'd damaged the surface so much when taking the old tiles off that the plasterer said he couldn't skim it... to my slight alarm he opted for plasterboard with (generous) dot and dab. But it worked.

Hoonabator

Original Poster:

604 posts

257 months

Friday 2nd December 2011
quotequote all
The problem I have is as mentioned above. The state the walls are in having removed an airing cupboard and the previous tiles were floor to ceiling so the walls are now a bit buggered.

As I'm only tiling to waist height and top half has to be skimmed. But it still leaves the lower half that is a skimmed plasterboard or plastered blockwork already??

Oh it was the guys at Mandarin Stone that raised this issue.

no eye deer

70 posts

184 months

Friday 2nd December 2011
quotequote all
Hi Hoon,

Dickymint is correct re the weight issue. Have a browse here for some idea as to the weight limits for various substrates, http://www.classical-flagstones.co.uk/CatalogData/...

Remember that it's not just the weight of the tiles but also the adhesive and grout that you have to factor in. The limits as you can imagine probably have a fairly wide safety margin built in but I wouldn't push my luck going too far over them.

regards

jeff



Hoonabator

Original Poster:

604 posts

257 months

Tuesday 20th December 2011
quotequote all
quick update.

Everyone I spoke to said not a good idea to put stone on the fresh skim.

Decided to skim down to the stone level only. Where the ceiling high stone was going in the shower area I stripped the old plasterboard and replace with the cement based stuff. Room is coming on nicely now. Cheers guys



dickymint

29,278 posts

289 months

Tuesday 20th December 2011
quotequote all
^^^ Nice, I like Trav. Now get it sealed and grouted by the morning. wink

Hoonabator

Original Poster:

604 posts

257 months

Tuesday 20th December 2011
quotequote all
All done today. Will post a finished pick once 2nd fix is done.