chris_chim said:
Offords in Cambridgeshire did mine a couple of weeks ago. Cost was a fair bit less than that (£900 inc VAT).
I understand they changed all the 24 bushes (shocks as well as wishbones) and most of the cost was labour - took them 2 days.
It was indeed Offords who quoted me the £1000 + VAT and 2 days labour.
FunkyGibbon said:
chris_chim said:
Offords in Cambridgeshire did mine a couple of weeks ago. Cost was a fair bit less than that (£900 inc VAT).
I understand they changed all the 24 bushes (shocks as well as wishbones) and most of the cost was labour - took them 2 days.
It was indeed Offords who quoted me the £1000 + VAT and 2 days labour.
seems they learnt from their mistake then, 900 incl vat is a bargain, i suspect they lost money on it ..
matthewbinns said:
joospeed said:
seems they learnt from their mistake then, 900 incl vat is a bargain, i suspect they lost money on it ..
yeah must be terrible only being able to get away with charging £60 per hour for a bloke weilding a spanner
900 pounds minus 260 pounds of bushes leaves 640 pounds, 2 days is 16 hours so 640 / 16 is 40 per hour incl vat .. sounds a bargain to me ..
joospeed said:
matthewbinns said:
joospeed said:
seems they learnt from their mistake then, 900 incl vat is a bargain, i suspect they lost money on it ..
yeah must be terrible only being able to get away with charging £60 per hour for a bloke weilding a spanner
900 pounds minus 260 pounds of bushes leaves 640 pounds, 2 days is 16 hours so 640 / 16 is 40 per hour incl vat .. sounds a bargain to me ..
yep - I'm happy with that. I just wanted to check the ball park figure.
Thanks
The powerflex bushes came to almost £17+VAT a piece and the labour was £420+VAT.
I have used Offords for quite a while now and always found their rates good value.
They may be playing safe by quoting £1000 as it is hard to predict how long the job will take (although they said mine was a b*st*rd).
I have used Offords for quite a while now and always found their rates good value.
They may be playing safe by quoting £1000 as it is hard to predict how long the job will take (although they said mine was a b*st*rd).
chris_chim said:So, what's the car like now then Chris?
The powerflex bushes came to almost £17+VAT a piece and the labour was £420+VAT.
I have used Offords for quite a while now and always found their rates good value.
They may be playing safe by quoting £1000 as it is hard to predict how long the job will take (although they said mine was a b*st*rd).
The front has definately sharpened up as that was where the biggest problem was (wishbones were up against the chassis). Initially the rear felt under damped (a bit 'bouncy' over bumps), don't understand why this should be.
It feels better now after a few hundred miles, don't know if this is because I am getting used to it or because something has settled down again.
It feels better now after a few hundred miles, don't know if this is because I am getting used to it or because something has settled down again.