Just so i know my legal standing for the future. If i use a supplier specified in a tender and they dont perform ie late delivery or dont put defects right promptly, is it just my companies problem or is the problem with my client who specified them?

LooneyTunes

9,543 posts

189 months

Friday 28th June 2013
quotequote all
What does the contract say about it?

If it's silent on the matter, which I hope it isn't, then it's time for a sensible conversation with the client if it looks like the supplier is going to underperform.

pistolar

Original Poster:

1,474 posts

299 months

Friday 28th June 2013
quotequote all
The contract tells us to use a specified supplier.
We then place an order with them.
The contrct is between us and the supplier.
Does my client have any legal responsibilty as they have specified a potentially useless supplier?

LooneyTunes

9,543 posts

189 months

Saturday 29th June 2013
quotequote all
I'd be tempted to bang this over to SP&L (more legal types on there).

My gut feeling is that if you are responsible for overall delivery, and there are no provisions in there regarding the pre-selected supplier and implications of any under-performance on their part, that there's scope for things to get messy.

I realise it may be after the horse is bolted but, whenever clients ask to give anything outside my direct control (even deliverables from their internal staff) the potential to impact overall delivery, provisions relating to this get baked into the contract.

New POD

3,851 posts

181 months

Saturday 29th June 2013
quotequote all
Years ago whilst working as an assembly engineer at a turbo charger manufacturer in skelmersdale, we had a number of quotes for a new assembly line, with a few alternatives on how to achieve it.

Our 'usual' supplier of automation, came up with a really good proposal, but one station, a test and setting station (sets the vanes on a VNT turbo to flow a particular flow at a particular pressure of air) was a bit vague. We were used to this with them, and they said "We'll go and talk to a few specialists and pick one"

On further questioning, one of the other companies in the list (who I had dealt with at another company, but who had no record with the company I was now with,) had also quoted us for the full job.

We ended up saying to both "Company A gets the job, if they use company B, but if not we use company C"
Company A ended up passing on part of the penalty clauses to company B, so if they failed because of company B, then company B would pay them.

anonymous-user

85 months

Monday 1st July 2013
quotequote all
Is it a specified supplier, or do you pick from the list, if the second you have no recourse to the buyer, if the first keep records of everything that goes wrong and your efforst to correct and manage, and then recomend termination to the buyer, if/when they stop ypu terminating you can start to argue they are responsible for the performance of the supplier.