Hello all,

I live in a tenement with 16 flats.

There has been various issues with the roof and various quotes for repair.

The selected contractor has quoted £6400 @ £400 per flat.

This contractor is not vat registered and I have a concern that we may be ripped off in some way shape or form.

How do I pay my share but have protection from loosing my money should it go wrong?

I do not believe the contractor can take a card payment.

Cheers

Dave

davepoth

29,395 posts

230 months

Wednesday 14th August 2013
quotequote all
Presumably it's been selected by the resident's association? I would have thought they would pay the contractor and then chase you up for it rather than everyone paying separately. Sounds like a complete nightmare.

ClaphamGT3

12,250 posts

274 months

Wednesday 14th August 2013
quotequote all
General Madness said:
Hello all,

I live in a tenement with 16 flats.

There has been various issues with the roof and various quotes for repair.

The selected contractor has quoted £6400 @ £400 per flat.

This contractor is not vat registered and I have a concern that we may be ripped off in some way shape or form.

How do I pay my share but have protection from loosing my money should it go wrong?

I do not believe the contractor can take a card payment.

Cheers

Dave
Is there a managing agent handling this on your behalf?

General Madness

Original Poster:

365 posts

183 months

Wednesday 14th August 2013
quotequote all
No official collective unfortunately. The tenent who has been dealing with it has suggested we all pay separately by cheque.

I just don't feel comfortable to pay that sort of amount without some form of security.

General Madness

Original Poster:

365 posts

183 months

Wednesday 14th August 2013
quotequote all

General Madness

Original Poster:

365 posts

183 months

Wednesday 14th August 2013
quotequote all
Just to add, I live in Edinburgh incase that makes any difference

creampuff

6,511 posts

174 months

Wednesday 14th August 2013
quotequote all
I quite often pay tradesmen in a way which gives me little comeback if it goes wrong. Otoh I make sure I have confidence in them before giving them the work.

I'd suggest the problem here is that the lack of VAT registration means a low turnover, which may also indicate they are hopeless.

ClaphamGT3

12,250 posts

274 months

Wednesday 14th August 2013
quotequote all
In the scheme of things a £6400 roofing job isn't a big job.

If you are that worried, you can try to hold back a retention of c £5-10k but, at that scale, they may well tell you jog on.

What exactly are your concerns?

creampuff

6,511 posts

174 months

Wednesday 14th August 2013
quotequote all
Is a £10000 retention on a £6400 job where the roofer pays you £3600 before he starts work?

General Madness

Original Poster:

365 posts

183 months

Wednesday 14th August 2013
quotequote all
ClaphamGT3 said:
In the scheme of things a £6400 roofing job isn't a big job.

If you are that worried, you can try to hold back a retention of c £5-10k but, at that scale, they may well tell you jog on.
What exactly are your concerns?
Yeah I do t think that will be happening.

I am not too sure really. Just don't want to waste money, I know what the quote is for and I am sure it's accurate.

ClaphamGT3

12,250 posts

274 months

Wednesday 14th August 2013
quotequote all
General Madness said:
ClaphamGT3 said:
In the scheme of things a £6400 roofing job isn't a big job.

If you are that worried, you can try to hold back a retention of c £5-10k but, at that scale, they may well tell you jog on.
What exactly are your concerns?
Yeah I do t think that will be happening.

I am not too sure really. Just don't want to waste money, I know what the quote is for and I am sure it's accurate.
If you're appointing directly then, realistically, retention is about the only real control you can exert. Who is going to agree with the contractor that he has satisfactorily completed the work?

General Madness

Original Poster:

365 posts

183 months

Wednesday 14th August 2013
quotequote all
ClaphamGT3 said:
If you're appointing directly then, realistically, retention is about the only real control you can exert. Who is going to agree with the contractor that he has satisfactorily completed the work?
You make some good points.

I think I will be suggesting holding off until the work is completed. From the email I received today it suggested to me they were wanting paid in full in advance.

valais

60,137 posts

186 months

Wednesday 14th August 2013
quotequote all
General Madness said:
I think I will be suggesting holding off until the work is completed. From the email I received today it suggested to me they were wanting paid in full in advance.
I suggest a residents meetings to set out:
  • How they were chosen (3 quotes?) - how do they compare as a competitive quote?
  • Payment (weekly phased or at end of job, never in advance - they have incurred no costs)
  • Warranty for work
  • References for work
How did this tenant select themselves to be the manager? Are they the most affected by the roof?

spitsfire

1,061 posts

166 months

Thursday 15th August 2013
quotequote all
Is the building factored?

If not, you are in all probability in for a massive ball-ache however you do it - the majority will go for the cheapest option available, everybody will bh and moan if you push for someone more appropriate to do the work, and you'll be left with the choice of not getting anything done or having a bad job done, which will in all probability make the problem worse.

Tenement roofs are very, very expensive to repair; especially slate roofs. A roofer who know what they're doing will be a damn site more expensive than that for anything more serious than a bit of flashing or a couple of broken tiles. If the roof has been leaking for a while, you'll probably find that the initial problem is only the start of it.

Sorry to be the bearer of bad news, but getting anything communal done in a tenement is a complete PITA. I nearly bought a flat in Glasgow which I had a lot of emotional attachment to, but was persuaded not to because the building wasn't factored and the chimney heads needed serious work. Was told that the only way the work was going to get done was if either I paid for it and then tried to recover the money from the other owners through the courts (they weren't willing to pay up), or got the Council to slap an statutory order on it, which is a nightmare in and of itself.

Red Devil

13,534 posts

239 months

Thursday 15th August 2013
quotequote all
General Madness said:
Just to add, I live in Edinburgh incase that makes any difference
Yes it does. Scotland is very different country from E&W in all sorts of ways.

spitsfire said:
Is the building factored?
A very good question
http://www.legislation.gov.uk/asp/2011/8/enacted

spitsfire said:
If not, you are in all probability in for a massive ball-ache however you do it - the majority will go for the cheapest option available, everybody will bh and moan if you push for someone more appropriate to do the work, and you'll be left with the choice of not getting anything done or having a bad job done, which will in all probability make the problem worse.

Tenement roofs are very, very expensive to repair; especially slate roofs. A roofer who know what they're doing will be a damn site more expensive than that for anything more serious than a bit of flashing or a couple of broken tiles. If the roof has been leaking for a while, you'll probably find that the initial problem is only the start of it.

Sorry to be the bearer of bad news, but getting anything communal done in a tenement is a complete PITA. I nearly bought a flat in Glasgow which I had a lot of emotional attachment to, but was persuaded not to because the building wasn't factored and the chimney heads needed serious work. Was told that the only way the work was going to get done was if either I paid for it and then tried to recover the money from the other owners through the courts (they weren't willing to pay up), or got the Council to slap an statutory order on it, which is a nightmare in and of itself.
The other question which needs answering is, if there is no factor, is there a TMS in place?
http://scotland.shelter.org.uk/get_advice/advice_t...

spitsfire

1,061 posts

166 months

Thursday 15th August 2013
quotequote all
Red Devil said:
The other question which needs answering is, if there is no factor, is there a TMS in place?
http://scotland.shelter.org.uk/get_advice/advice_t...
Excellent link, although from what has been posted, I doubt it.

I had a chat with a friend back home the other evening about the tenement next door to them in Glasgow which has had a leaking roof for a couple of years. The joists in the front of the building have started to rot, causing the area around the bay windows to subside and the lintels have started to show stress cracks. This is because one owner blocks any spending on the property, and another won't kick up unless everybody chips in equally. The end result? They're now looking at a bill for 100k+, and the guy who won't spend anything is still refusing to get the initial repair done. Complete PITA.

Check out the number of court cases over common repairs in Westlaw, and you'll realise quite how dysfunctional the whole thing is.

General Madness

Original Poster:

365 posts

183 months

Thursday 15th August 2013
quotequote all
Thanks for all the responses.

There is no official party in charge of the repairs.

2 fellow owners have requested at least 4 quotes for repair from various companies. The company that has been selected provided a detailed quote with pictures of the damage. They also are the most competitively priced.

I am happy enough with the process so far.

My share of £400 is a substantial amount of money to my family and I don't really want to pay until I am confident that the work has been completed correctly.

How do I go about withholding payment until completion without causing any grief for the other residents?

surveyor

18,713 posts

215 months

Thursday 15th August 2013
quotequote all
My suggestion would be to appoint a building surveyor to oversea the works and agree a stage payment with the contractor.

I'd imagine the contractor would want to know that funds are sitting in the surveyors client account and are available...

Garvin

5,675 posts

208 months

Thursday 15th August 2013
quotequote all
surveyor said:
My suggestion would be to appoint a building surveyor to oversea the works and agree a stage payment with the contractor.

I'd imagine the contractor would want to know that funds are sitting in the surveyors client account and are available...
^^^^^ This. Whenever I have building work, or the like done, I always agree a stage payment plan and an important part of that is to only pay substantial amounts on delivery of any goods and materials to site as well as stages of progress. I also retain 5% for up to six months after completion to ensure the contractor is motivated to come back and sort out any problems that might occur. Contractors don't like it but such terms can be negotiated if you're determined enough.

spitsfire

1,061 posts

166 months

Thursday 15th August 2013
quotequote all
What is the problem? Can you upload the photos?