Planning application - 8 week decision period
Discussion
I have been assisting my local tennis club with a planning application for 4 courts on a large site owned by the local cricket club. The application was made and registered in December and a decision should be made tomorrow (11th February). On the 30th January the council asked for a report upon bats(not that there are any)and calculations to prove that light from the floodlights will not affect the neighbours (50m away) and asked that we withdraw the application and reapply when the info is available. We'll get the the two reports today and can email them today, but the council have now emailed saying that they will refuse permission as they will not have time to assess the reports by tomorrow, and again have asked that we withdraw.
I realise that the council is taking this attitude to look good in government performance tables but MUST they refuse or can they grant (albeit reluctantly)another week or two? IIRC from doing planning apps years ago the council regularly took longer than 8 weeks so why cannot it now? It seems to me that they should have asked for this information when checking the application 2 months ago and they have asked too late in the day knowing full well that we could not reasonably be expected to achieve the time frame.
Must we go along with what they want or can we insist on having longer?
I realise that the council is taking this attitude to look good in government performance tables but MUST they refuse or can they grant (albeit reluctantly)another week or two? IIRC from doing planning apps years ago the council regularly took longer than 8 weeks so why cannot it now? It seems to me that they should have asked for this information when checking the application 2 months ago and they have asked too late in the day knowing full well that we could not reasonably be expected to achieve the time frame.
Must we go along with what they want or can we insist on having longer?
It sounds like the planning officer is going to deal with the application under delegated powers rather than putting it in front of the committee. If they're worried about missing targets that's their issue. Perhaps you could agree to a time extension of a specified amount to give them time to look at the info, or agree a renewed application with the fee waived.
Be wary of this being a ruse to allow disgruntled objectors a chance to lodge objections they were out of time with on the original application.
Be wary of this being a ruse to allow disgruntled objectors a chance to lodge objections they were out of time with on the original application.
Hi developer here...
Perfectly normal I'm afraid. They'll normally ask for the extra info they want towards the end when they eventually look at the file. It is a big black mark to go over the target period so they ask you to withdraw or refuse. If they refuse they application they have determined it within the timescales. You ofcourse can appeal but that doesn't effect the determination timescales and targets.
basically it is a load of CRAP....
All I can suggest is play the game and just call them a bunch of whatevers....
Perfectly normal I'm afraid. They'll normally ask for the extra info they want towards the end when they eventually look at the file. It is a big black mark to go over the target period so they ask you to withdraw or refuse. If they refuse they application they have determined it within the timescales. You ofcourse can appeal but that doesn't effect the determination timescales and targets.
basically it is a load of CRAP....
All I can suggest is play the game and just call them a bunch of whatevers....
I would be tempted to phone the case officer and grant them the extension they need.
Explain how keen you are to proceed with the project on site , and basically , beg
.
They do not have to determine an application in the given 8 weeks IF they have requested additional information, but some councils have their own rules on how they deal with these situations.
Bat reports are causing serious problems nowadays , one local authority I deal with regularly, and have done for 35 years, just introduced a new rule that applications that may require a Bat Report will not even be registered unless the information is submitted at day 1.
Explain how keen you are to proceed with the project on site , and basically , beg
.They do not have to determine an application in the given 8 weeks IF they have requested additional information, but some councils have their own rules on how they deal with these situations.
Bat reports are causing serious problems nowadays , one local authority I deal with regularly, and have done for 35 years, just introduced a new rule that applications that may require a Bat Report will not even be registered unless the information is submitted at day 1.
Busa mav said:
Bat reports are causing serious problems nowadays , one local authority I deal with regularly, and have done for 35 years, just introduced a new rule that applications that may require a Bat Report will not even be registered unless the information is submitted at day 1.
They have probably done this to speed things up. One of the regularly used objections to redevelopment is "think of the bats", even if there is none!I'm not au fait with the details of planning applications but I would presume that previously the LA would have to commission a Bat Report whereas now (in this case) the developer has to pay for it?