Business Electricity - Power required? Phase 3?
Business Electricity - Power required? Phase 3?
Author
Discussion

JLammy

Original Poster:

89 posts

174 months

Wednesday 2nd April 2014
quotequote all
I am currently in discussion with a shopping centre for kiosk/mall space. They have asked me what type of power do I need; Whether it's single phase, phase 3 etc. Would anyone be able to tell me what I would need?

The following list is all of the equipment I intend on using:

- Till (100W)
- 2 Blenders (950W)
- Water Urns (900W)
- Freezer (450W)
- Fridge (450W)
- Portable Induction Hob (3600W)

I don't know if this makes a difference, but they have told me that a fuse-board (with x number of plug sockets) would need to be installed to the kiosk, and then this fuse-board will have one line connected to ONE of the shopping centre's plug sockets.

Any help would be much appreciated.

AdeTuono

7,626 posts

258 months

Wednesday 2nd April 2014
quotequote all
Will you be running all that ^^^^ concurrently?

eliot

11,999 posts

285 months

Wednesday 2nd April 2014
quotequote all
would the fridge freezers really use a kilowatt between them? seems high.

Jonny_

4,729 posts

238 months

Wednesday 2nd April 2014
quotequote all
Single phase = anything that runs from a normal 230 or 240v supply.

Three phase = heavy loads that run from an industrial 400 or 415v supply.

Nothing you list is likely to need a 3 phase supply, however you can run a single phase load from one phase of a 3 phase supply.

The calculations for sizing your supply aren't as straightforward as they might be, it's easy enough to add up the wattages and divide by 230 volts to get an idea of your maximum total current draw, which suggests you'd be ok with a 32A single phase supply, but this is a very simplistic estimate.

JLammy

Original Poster:

89 posts

174 months

Thursday 3rd April 2014
quotequote all
AdeTuono said:
Will you be running all that ^^^^ concurrently?
There will be times where all will be concurrently from the fuse-board which is then connected to the one socket in the shopping centre.

eliot said:
would the fridge freezers really use a kilowatt between them? seems high.
Not too sure on this. But the kiosk manufacturer has given me this data, so I assumed they were correct?

Jonny_ said:
Single phase = anything that runs from a normal 230 or 240v supply.

Three phase = heavy loads that run from an industrial 400 or 415v supply.

Nothing you list is likely to need a 3 phase supply, however you can run a single phase load from one phase of a 3 phase supply.

The calculations for sizing your supply aren't as straightforward as they might be, it's easy enough to add up the wattages and divide by 230 volts to get an idea of your maximum total current draw, which suggests you'd be ok with a 32A single phase supply, but this is a very simplistic estimate.
Thanks a lot for the reply. But would connecting all of those in the list and running them at the same time cause any problems on a single phase supply?

Edited by JLammy on Thursday 3rd April 00:36

MrSparks

655 posts

151 months

Thursday 3rd April 2014
quotequote all
If all of that kit was on, at full power, at one time you'd be using 6450 watts which is 28 amps. All of that equipment would be single phase at a guess (3 pin standard plugs).

If you're sure that you'll be using all of it at once, on full power then you're going to need a supply of at least 28amps. I would hazard a guess that the shopping centre have commando sockets protected by RCD dotted around (large blue plugs) which are quite likely to be 32amps. Most shopping centres/malls/car boots/markets I've worked at would have a fuse board connected to a 32a commando plug which then plugs into the fixed commando socket on the site.

So I would assume that they'll offer you a 32 amp single phase supply which will be adequate for your needs (based on the above). Anything less and you'll have to be careful what you're using at any one time wink