Builder asking for large deposit - how to protect myself
Discussion
Ive been shopping around for a builder for ages, and finally found one we really like and seems to really know his stuff.
However he hasn't been trading for too long, a few years at max, and he is asking for a 25% deposit (tens of thousands of pounds), the rest of the payments (25%) at stage payments, so 4 25% payments, last one not till completion and sign off.
Im 100% happy with the 3 25% stage payments, it's the deposit that scares me, he wont be starting work on the build for a couple of months, if he goes bust, or disappears I'm pretty screwed.
Ive been to his house, met his wife, I've seen some of his buildings, so i dont doubt him or think he is scamming me, just scared of loosing the money.
Any way to protect the 25% deposit, if he was to go bust would i ever see a penny?
Ive tried negioating with him, but he said this is how he works and he needs the deposit to start sourcing materials etc
Thanks
However he hasn't been trading for too long, a few years at max, and he is asking for a 25% deposit (tens of thousands of pounds), the rest of the payments (25%) at stage payments, so 4 25% payments, last one not till completion and sign off.
Im 100% happy with the 3 25% stage payments, it's the deposit that scares me, he wont be starting work on the build for a couple of months, if he goes bust, or disappears I'm pretty screwed.
Ive been to his house, met his wife, I've seen some of his buildings, so i dont doubt him or think he is scamming me, just scared of loosing the money.
Any way to protect the 25% deposit, if he was to go bust would i ever see a penny?
Ive tried negioating with him, but he said this is how he works and he needs the deposit to start sourcing materials etc
Thanks
http://www.ribacontracts.com/
You can get standard contracts here...
Or for smaller projects here:
http://www.sandwell.gov.uk/downloads/file/1038/bui...
(staged with 5% retained)
You can get standard contracts here...
Or for smaller projects here:
http://www.sandwell.gov.uk/downloads/file/1038/bui...
(staged with 5% retained)
This isn't bricks and timber from the local travis perkins, this is a bespoke treehouse build, of which Ive specked most of the materials and finishes to use, think craftsmen, local timbermills, online suppliers of very niche products (hand made copper bathtubs, handmade hardwood windows etc)
SantaBarbara said:
You both need to draw up a contract.
Do they have pro forma contracts available
No much protection if he goes into liquidation, happened to a good friend of mine on a large scale extension - fixed price, staged payments etc but he still ended up shelling out again with someone else to get it completed.Do they have pro forma contracts available
Only option I can think of is to pay for the materials yourself (at his trade discount) for delivery to you and pay him a smaller deposit to secure the labour slot.
Perhaps have a solicitor hold the funds in escrow for you? Builder can call off against them on a mutually agreeable basis. It shouldn't be too hard to draw up a simple process to release the funds. You'll pay for the solicitors time, and probably some handling fees but perhaps worth it for the peace of mind.
walamai said:
Perhaps have a solicitor hold the funds in escrow for you? Builder can call off against them on a mutually agreeable basis. It shouldn't be too hard to draw up a simple process to release the funds. You'll pay for the solicitors time, and probably some handling fees but perhaps worth it for the peace of mind.
What if the builder doesn't accept that?I don't think he will
I would be extremely nervous of any contractor who can't fund the cash flow on the work that they're taking on. If you really want this guy, pay for the materials direct but I would think very carefully whether they have the business resilience to take on a contract of the size that you're asking of them