Leased line installation - how quickly?
Leased line installation - how quickly?
Author
Discussion

shopper150

Original Poster:

1,583 posts

225 months

Sunday 14th October 2018
quotequote all
I’m trying to get an internet connection installed in a premises that used to have a leased line connected, the BT hardware for this appears to still be onsite.

Is it a quick process to get this connection back up and running (the previous occupants of the premesis have cancelled the connection)?

I have an order for BT FTTP in place and BT/Openreach keep missing appointments, it’s been nearly 6 weeks so far.

Alternatively, There is an active phone line there, would be be quicker to get normal FTTC to get us up and running?

anonymous-user

85 months

Sunday 14th October 2018
quotequote all
It's been over 10 years since I regularly ordered these, but Leased Lines used to take around 1 month, IF, and it's a big IF, the multiple departments involved send the correct MUX units, adapters, etc.

After a while, I became quite good at getting all the ducks in a row for a one month install as I know which hardware was needed and chased it if it didn't arrive.

After a while it was replaced with internet presented as Ethernet by ISPs and took all the pain out of BT leased lines

CAPP0

20,881 posts

234 months

Sunday 14th October 2018
quotequote all
BT often quote 60 working days for this type of install. Can sometimes be done sooner/quicker but no guarantees.

Also, is there any question/issue around wayleave with the building? Just because there was a line in there previously doesn't automatically mean the landlord won't demand a new wayleave for the new service. And there is absolutely no way to estimate elapsed time on that, unfortunately.

shopper150

Original Poster:

1,583 posts

225 months

Sunday 14th October 2018
quotequote all
I have no idea about wayleave, I need to look into it!

Is it quicker to consider anothe provider or are the timescales ultimately determined by BT anyway?

giveitfish

4,423 posts

245 months

Sunday 14th October 2018
quotequote all
6 to 8 weeks every time in my experience, except the one which needed out of hours road digging which took 8 months eek

petemurphy

10,973 posts

214 months

Sunday 14th October 2018
quotequote all
about 3,000 years if its bt

CAPP0

20,881 posts

234 months

Sunday 14th October 2018
quotequote all
shopper150 said:
I have no idea about wayleave, I need to look into it!

Is it quicker to consider anothe provider or are the timescales ultimately determined by BT anyway?
The wayleave and the provision, whilst inextricably linked, are two different things - so whilst you need the wayleave before the circuit can be installed, they'll happen independently. Wayleaves will be sorted by landlords and lawyers!