Overflow pipe drilled through DPC
Overflow pipe drilled through DPC
Author
Discussion

Mr Creosote

Original Poster:

202 posts

12 months

Sunday 24th May
quotequote all
The previous owner of our house had a water softener installed, and I’ve only just twigged that the installer most likely drilled through the DPC to fit the overflow. See below. The exterior DPC sits just above the air brick.



I believe we have a stepped DPC/cavity trays (I asked here previously about water splashing my walls and was told as much) so presumably this pipe goes straight through it.

I haven’t noticed any damp issues because of this, but how much of a big deal is this, and should I do anything about it?

CambsBill

2,437 posts

205 months

Sunday 24th May
quotequote all
Unless the hole is lower on the inside than on the outside then he hasn't drilled through the dpc, just straight through the brick.

InitialDave

14,927 posts

146 months

Sunday 24th May
quotequote all
I agree, it looks like it's just above the DPC based on your description.

smokey mow

1,383 posts

227 months

Sunday 24th May
quotequote all
You should have a cavity tray installed above the air brick so yes it will have been drilled through to fit the pipe.

The purpose of the cavity tray is to deflect any moisture and condensation in the cavity to the outside and prevent it from pooling on the top of the air brick where it could then soak to the inside blockwork.

What they’ve done is wrong but if you’ve not noticed any issues then it’s likely not going to be a problem.


sherman

15,140 posts

242 months

Sunday 24th May
quotequote all
I would be filling the gap in the hole with some brown silicone. Thats an ideal access point for a mouse.

Mr Creosote

Original Poster:

202 posts

12 months

Monday 25th May
quotequote all
sherman said:
I would be filling the gap in the hole with some brown silicone. Thats an ideal access point for a mouse.
Good point. Thanks.

Mr Creosote

Original Poster:

202 posts

12 months

Monday 25th May
quotequote all
smokey mow said:
You should have a cavity tray installed above the air brick so yes it will have been drilled through to fit the pipe.

The purpose of the cavity tray is to deflect any moisture and condensation in the cavity to the outside and prevent it from pooling on the top of the air brick where it could then soak to the inside blockwork.

What they ve done is wrong but if you ve not noticed any issues then it s likely not going to be a problem.
Thanks. If I do get issues, what would the solution be? Presumably we’d have to remove bricks to patch the DPC? Is this a big job?

smokey mow

1,383 posts

227 months

Monday 25th May
quotequote all
Mr Creosote said:
Thanks. If I do get issues, what would the solution be? Presumably we d have to remove bricks to patch the DPC? Is this a big job?
Pretty much as you describe. Take 3 or 4 bricks out above the air brick which should then give enough room to lap in a new tray. Replace bricks and then make good.

Roughly half a days work for a competent builder.

Mr Creosote

Original Poster:

202 posts

12 months

Monday 25th May
quotequote all
Thanks!