How long for concrete/screed to dry ?
Discussion
Am having a conservatory added to the house at the moment......spoke to company yesterday after foundations completed, and should be put up in 2 weeks from now....all good so far.........
Then comes the interesting bit....they ask me what type of flooring I'm having, so I say vinyl......then they say I have to allow one week per 0.5 inch of concrete/screed to allow it to dry after they've done........now they've put down 4 inches of concrete and will be putting down another 3 inches of screed......so this means I can't put flooring down until 14 weeks after completion.....which will be Xmas.......sounds bonkers to me.
Anyone know if this is right or if they're simply covering their arse ?
Then comes the interesting bit....they ask me what type of flooring I'm having, so I say vinyl......then they say I have to allow one week per 0.5 inch of concrete/screed to allow it to dry after they've done........now they've put down 4 inches of concrete and will be putting down another 3 inches of screed......so this means I can't put flooring down until 14 weeks after completion.....which will be Xmas.......sounds bonkers to me.
Anyone know if this is right or if they're simply covering their arse ?
captainzep said:
dxg said:
Should I be pedantic and point out that concrete doesn't dry?
Bloody posters trying to be a bit 'surreal' and funny.Get back on topic and try to be helpful to the OP. Kay?
I don't know about the statistics but when we had a new concrete floor in our kitchen it we put a new vinyl floor down about 6 weeks after they had finished and within a week it had bubbled and rucked.
The floor man said it was OK but a surveyor friend of my husband came to look at it and used a moisture detecting gadget. He told us we should have waited another 3 months!
The firm eventually came back after about 3 months of arguing and relaid the vinyl and also put some black goo down as well and we never had any problems afterwards.
The floor man said it was OK but a surveyor friend of my husband came to look at it and used a moisture detecting gadget. He told us we should have waited another 3 months!
The firm eventually came back after about 3 months of arguing and relaid the vinyl and also put some black goo down as well and we never had any problems afterwards.