Hatfield Tunnel Contaflow Closures - 2 Years from mid 2009
Discussion
I might be jumping the gun with this, but if anyone was considering moving house along the Hertfordshire A1(M) corridor they might like a heads up.
Basically it seems each tunnel will be shut with contraflow in the other tunnel.
Start on site 22nd May 2009
Close north tunnel 25th July 2009
Open north tunnel 15th May 2010
Close south tunnel 15th May 2010
Open south tunnel 11th April 2011
Project Completion 11th April 2011
Report http://coins.welhat.gov.uk/ViewSelectedDocument.as...
Basically it seems each tunnel will be shut with contraflow in the other tunnel.
Start on site 22nd May 2009
Close north tunnel 25th July 2009
Open north tunnel 15th May 2010
Close south tunnel 15th May 2010
Open south tunnel 11th April 2011
Project Completion 11th April 2011
Report http://coins.welhat.gov.uk/ViewSelectedDocument.as...