A note for self builders
Discussion
I have just been told by the electricity company that it takes 3-4 months to relocate the temporary supply to the house!!!
Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate
Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate

Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
satans worm said:
I have just been told by the electricity company that it takes 3-4 months to relocate the temporary supply to the house!!!
Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate
Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
Can you not lay your own cable & install the kit yourself (i.e. get an electrician to do it) and then just get the E-board to connect it up?Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate

Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
Iain328 said:
satans worm said:
I have just been told by the electricity company that it takes 3-4 months to relocate the temporary supply to the house!!!
Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate
Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
Can you not lay your own cable & install the kit yourself (i.e. get an electrician to do it) and then just get the E-board to connect it up?Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate

Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
Will have a word with our sparky, we desparetly need to get the boiler on so we can get the UFH heating on, then turn it off again and lay the wood flooring, before Christmas!
satans worm said:
I have just been told by the electricity company that it takes 3-4 months to relocate the temporary supply to the house!!!
Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate
Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
we had a quote to bury a cable across a field so we didnt have a telegraph pole in view, about 120m - £12k.... i'm getting used to that pole now.. Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate

Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
Iain328 said:
satans worm said:
I have just been told by the electricity company that it takes 3-4 months to relocate the temporary supply to the house!!!
Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate
Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
Can you not lay your own cable & install the kit yourself (i.e. get an electrician to do it) and then just get the E-board to connect it up?Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate

Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
rsv gone! said:
Iain328 said:
satans worm said:
I have just been told by the electricity company that it takes 3-4 months to relocate the temporary supply to the house!!!
Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate
Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
Can you not lay your own cable & install the kit yourself (i.e. get an electrician to do it) and then just get the E-board to connect it up?Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate

Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
(The low point looking very short thanks to PH
)Edited by satans worm on Wednesday 12th November 14:29
satans worm said:
rsv gone! said:
Iain328 said:
satans worm said:
I have just been told by the electricity company that it takes 3-4 months to relocate the temporary supply to the house!!!
Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate
Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
Can you not lay your own cable & install the kit yourself (i.e. get an electrician to do it) and then just get the E-board to connect it up?Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate

Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.

garyhun said:
satans worm said:
rsv gone! said:
Iain328 said:
satans worm said:
I have just been told by the electricity company that it takes 3-4 months to relocate the temporary supply to the house!!!
Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate
Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
Can you not lay your own cable & install the kit yourself (i.e. get an electrician to do it) and then just get the E-board to connect it up?Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate

Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.

Its also quite hard PM when both you and your wife are doing min 14hour days at work ontop of building a house!
Still, the experience has been great and we will know how to be more efficient at it next time!!
satans worm said:
garyhun said:
satans worm said:
rsv gone! said:
Iain328 said:
satans worm said:
I have just been told by the electricity company that it takes 3-4 months to relocate the temporary supply to the house!!!
Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate
Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.
Can you not lay your own cable & install the kit yourself (i.e. get an electrician to do it) and then just get the E-board to connect it up?Their goes the Christmas deadline, we gonna be lucky to be in by spring at this rate

Really cant believe how long it takes to lay a 40m wire!!(It also costs around GBP1.5-2.5k!!)
This is a low point.

Its also quite hard PM when both you and your wife are doing min 14hour days at work ontop of building a house!
Still, the experience has been great and we will know how to be more efficient at it next time!!
anonymous said:
[redacted]
This is why a lot of property development falls at the last hurdle with interest being paid on loans until they the houses are sold.If you are going to self build it pays to get into early discussions with the local service providers at the planning stage to ensure you are looking at the connection, not waiting for it.
I have run Tower Cranes on generators for up to two years, as long as they are earthed and you get can get diesel to them they are fine and reasonably quiet.
Whats the rest of the project like?
Is the temperary supply meter already on a board somewhere. If so leave it there, build a small brick enclosure round it and run your own armoured cable to a new submain in the house with consumer unit. You therefore do not need to involve the elec board at all.
Tis easy. we do it all the time.
Tis easy. we do it all the time.
ALawson said:
anonymous said:
[redacted]
This is why a lot of property development falls at the last hurdle with interest being paid on loans until they the houses are sold.If you are going to self build it pays to get into early discussions with the local service providers at the planning stage to ensure you are looking at the connection, not waiting for it.
I have run Tower Cranes on generators for up to two years, as long as they are earthed and you get can get diesel to them they are fine and reasonably quiet.
Whats the rest of the project like?
satans worm said:
ALawson said:
anonymous said:
[redacted]
This is why a lot of property development falls at the last hurdle with interest being paid on loans until they the houses are sold.If you are going to self build it pays to get into early discussions with the local service providers at the planning stage to ensure you are looking at the connection, not waiting for it.
I have run Tower Cranes on generators for up to two years, as long as they are earthed and you get can get diesel to them they are fine and reasonably quiet.
Whats the rest of the project like?
Damned if I can remember the companies name but if your interested PM me and i'll dig out the details.
satans worm said:
NDA said:
Have you got a choice of leccy suppliers in your area? I would have thought there would be some competition allowing you an earlier connection date.
Interesting point 
I got quoted by EDF, who supplies, can ANY supplier do the leccy tie up then?
TedMaul said:
satans worm said:
NDA said:
Have you got a choice of leccy suppliers in your area? I would have thought there would be some competition allowing you an earlier connection date.
Interesting point 
I got quoted by EDF, who supplies, can ANY supplier do the leccy tie up then?