I've worked out how to RAG score based on date, but can't for the life of me get a formula to work for showing how many days something has to deliver. Any ideas?

I want it to look at the expected date to finish and say how many days are left to implement, but using =NETWORKDAYS doesn't work for some reason, unless I manually type in the current date and then I have to change it every day.

Pulse

Original Poster:

10,922 posts

220 months

Monday 25th October 2010
quotequote all
Never mind! The other half just did it for me!! Didn't realise she was a guru.

nickd01

625 posts

217 months

Monday 25th October 2010
quotequote all
If you have both cells as a date, you can simply subtract them.
I don't have a version other than Excel 2010 here, but for the older ones you may need to format the answer cell to show it as days.