Train crash in Scotland

Author
Discussion

Rick101

6,977 posts

152 months

Thursday 27th August 2020
quotequote all
Correct. Line was proved clear by the train ahead.

Whilst landslips can happen, this was an exceptional circumstance. Sinkholes happen, that does not mean all cars should be limited to 5mph forevermore just in case.

saaby93

32,038 posts

180 months

Thursday 27th August 2020
quotequote all
anonymous said:
[redacted]
Did the first train travel so slowly there was a two hour gap until giving the ok to the second one

P5BNij

15,875 posts

108 months

Thursday 27th August 2020
quotequote all
saaby93 said:
anonymous said:
[redacted]
Did the first train travel so slowly there was a two hour gap until giving the ok to the second one
We'll find out soon enough.

The longest I've been held anywhere awaiting a decision from Control was six hours in Knighton Loop just south of Leicester when a broken rail was discovered a little further on at Wigston.

essayer

9,127 posts

196 months

Thursday 27th August 2020
quotequote all
We all complain when stuck on a delayed train, but fking hell, imagine being stuck for two hours, then on the way back to where you started from, a derailment like this to occur frown

sim72

4,946 posts

136 months

Thursday 27th August 2020
quotequote all
saaby93 said:
anonymous said:
[redacted]
Did the first train travel so slowly there was a two hour gap until giving the ok to the second one
Timeline appears to be thus
0639: The down train (2B13) departs Montrose
0657: 2B13 (which is then just south of Carmont) reports landslip on the up line
0659: 1T08 is stopped at Carmont SB
0713: 2B13 arrives at Stonehaven but is then terminated due to flooding between there and Aberdeen.
c0700-0910: Investigation of up line takes place, it is determined that 1T08 cannot continue
0910: 2B13 is moved out of the way at Stonehaven so that 1T08 can arrive there
0925: 1T08 is moved across onto the down line
0936: 1T08 departs northbound
0938: 1T08 is derailed

Therefore there was about two and half hours between 2B13 and 1T08.

Ironically, it appears that the initial report of the up line landslip by 2B13 was only *just* in time to stop 1T08 in the first place.


Europa1

10,923 posts

190 months

Thursday 27th August 2020
quotequote all
essayer said:
We all complain when stuck on a delayed train, but fking hell, imagine being stuck for two hours, then on the way back to where you started from, a derailment like this to occur frown
Especially dying in it. rolleyes

matchmaker

8,530 posts

202 months

Friday 28th August 2020
quotequote all
sim72 said:
saaby93 said:
anonymous said:
[redacted]
Did the first train travel so slowly there was a two hour gap until giving the ok to the second one
Timeline appears to be thus
0639: The down train (2B13) departs Montrose
0657: 2B13 (which is then just south of Carmont) reports landslip on the up line
0659: 1T08 is stopped at Carmont SB
0713: 2B13 arrives at Stonehaven but is then terminated due to flooding between there and Aberdeen.
c0700-0910: Investigation of up line takes place, it is determined that 1T08 cannot continue
0910: 2B13 is moved out of the way at Stonehaven so that 1T08 can arrive there
0925: 1T08 is moved across onto the down line
0936: 1T08 departs northbound
0938: 1T08 is derailed

Therefore there was about two and half hours between 2B13 and 1T08.

Ironically, it appears that the initial report of the up line landslip by 2B13 was only *just* in time to stop 1T08 in the first place.
I'd say, having read the interim RAIB reports, that the above is broadly speaking, correct. The only point I'd amend/add to is the period c0700-0910. Part of the delay is that the points that 1T08 had to use to cross from the up line to the down line are what is termed "trailing points". Any points that a train carrying passengers traverses must be locked to avoid the points being "split" by the passage of a train (the failure of such a mechanism caused the Grayrigg derailment). The trailing points at Carmont did not have such a feature, so a MOM - Mobile Operations Manager - was dispatched by road to Carmont to put a physical lock on the points - known as "clipping". One this had been done 1T08 could proceed.

That's in the RAIB reports.

Whatsmyname

944 posts

79 months

Friday 28th August 2020
quotequote all
How much of that is in the report because a lot of it bksks.

gooner1

10,223 posts

181 months

Friday 28th August 2020
quotequote all
Whatsmyname said:
How much of that is in the report because a lot of it bksks.
For example?

matchmaker

8,530 posts

202 months

Friday 28th August 2020
quotequote all
Whatsmyname said:
How much of that is in the report because a lot of it bksks.
OK, what parts are bks?

Whatsmyname

944 posts

79 months

Friday 28th August 2020
quotequote all
I’m a bit time poor at the minute but I’ll read the report and try to explain it a lot better and post something this evening if you like.

matchmaker

8,530 posts

202 months

Friday 28th August 2020
quotequote all
I'd better correct what I posted earlier about the crossing at Carmont. I had thought it was mentioned in the RAIB report, but having reread the report I must have picked some information up elsewhere. In general what I wrote about passenger trains using unlocked points is correct - the points must be physically locked open or shut by being clamped manually. I understood that a manager had to be dispatched to Carmont to do this.

If I've caused any confusion, apologies. My railway signalling comes from an earlier era!



alangla

4,934 posts

183 months

Friday 28th August 2020
quotequote all
matchmaker said:
If I've caused any confusion, apologies. My railway signalling comes from an earlier era!

So does Carmont's...

Whatsmyname

944 posts

79 months

Friday 28th August 2020
quotequote all
Doesn’t really matter the age of the signalling the rules “principles” are pretty much the same.

Robertj21a

16,540 posts

107 months

Friday 28th August 2020
quotequote all
Whatsmyname said:
How much of that is in the report because a lot of it bksks.
Why don't you just read the report ?

Whatsmyname

944 posts

79 months

Friday 28th August 2020
quotequote all
Robertj21a said:
Why don't you just read the report ?
You could just read a bit above and see why. I’m on my phone and out and about at the minute.

Robertj21a

16,540 posts

107 months

Friday 28th August 2020
quotequote all
Whatsmyname said:
Robertj21a said:
Why don't you just read the report ?
You could just read a bit above and see why. I’m on my phone and out and about at the minute.
Nobody asked you to read it this minute.

coppernorks

1,919 posts

48 months

Friday 28th August 2020
quotequote all
matchmaker said:
I'd better correct what I posted earlier about the crossing at Carmont. I had thought it was mentioned in the RAIB report, but having reread the report I must have picked some information up elsewhere. In general what I wrote about passenger trains using unlocked points is correct - the points must be physically locked open or shut by being clamped manually. I understood that a manager had to be dispatched to Carmont to do this.

If I've caused any confusion, apologies. My railway signalling comes from an earlier era!

Yes, many sigboxes don't have point locks or powered crossovers, these boxes are not required to use their
crossovers much, just for engineering purposes and emergency occasions like this.

Had the train been empty of passengers and running as empty stock this "Clamp and Scotch " procedure
would not be necessary, but as the train had passengers on it the crossover had to be secured.

In the old days such a task would have been the signaller's job, but now a
MOM is required thus wasting huge amounts of time finding one and them travelling to the location.

IJWS15

1,877 posts

87 months

Friday 28th August 2020
quotequote all
anonymous said:
[redacted]
Polmont was carriages and a 47 so 3 link (probably screw) couplings, HST (IIRC) has buckeyes between all cars so much more rigid and less likely to concertina.

Most multiple units are now bolted joints between the units

Whatsmyname

944 posts

79 months

Friday 28th August 2020
quotequote all
Ok so we have a set of mechanical points that we are gonna go send an empty rain over In the facing direction, they have no facing point lock as they are predominantly trailing. What proves the correct position of the switch rail to within 5mm tolerance? Or do you just pull the lever and yolo it? Presuming no clip and scotch.