Moved Windows On New Build - Now Selling - Issue ?

Moved Windows On New Build - Now Selling - Issue ?

Author
Discussion

Renovation

Original Poster:

1,763 posts

123 months

Monday 1st September 2014
quotequote all
I built a new house approx 2 years ago.

During the build I changed internal walls etc which I believe isn't an issue (from a 3 bed to a 5 bed)

However I also moved one roof light from the side to the rear and added a second roof light also to the rear.

No one has noticed / cared and I've got the Completion Cert. etc

I'm now selling and wondering if I will have an issue - as they are both facing over my rear garden I'm aware I don't need planning for them but I do need Building Regs - whilst the house has been signed off for Building Regs at the time they weren't on the Planning Application so technically I didn't have the PD Rights to install them at the time.

Will anyone care ?

z4emsee

121 posts

146 months

Monday 1st September 2014
quotequote all
I very much doubt it will be a problem. If the surveyor spots it he's being extremely observant! Might lead to you needing the obligatory indemnity but it depends on the purchasers viewpoint. Is it not pd to put rooflights in once work is complete?

Spudler

3,985 posts

198 months

Monday 1st September 2014
quotequote all
Personally I wouldn't give it another thought.

x 7usc

1,423 posts

197 months

Tuesday 2nd September 2014
quotequote all
Spudler said:
Personally I wouldn't give it another thought.
100% this, i have my doubts it will be spotted and besides, your 1st thought is right, no one will care

Croutons

10,026 posts

168 months

Tuesday 2nd September 2014
quotequote all
"any alterations to the property?" Well yes, you have permission for one thing, and have done another, so you'll need to come clean on the forms. If it doesn't freak a buyer (given the house is so new), then their sol will want either Regs or an indemnity I would think, £100 maybe? I'd be prepared to swallow that as a minimum, given the 4 year enforcement period.

worsy

5,837 posts

177 months

Tuesday 2nd September 2014
quotequote all
He's not made any alterations to the property. They were put in during build.

Croutons

10,026 posts

168 months

Tuesday 2nd September 2014
quotequote all
worsy said:
He's not made any alterations to the property. They were put in during build.
Without permission, so the plans which were approved do not correspond to whats on the ground, or you could ask for permission for one thing and do something entirely different. Clearly that does not work, irrespecitve of the scale of change, its not what was approved.

Spare tyre

9,775 posts

132 months

Tuesday 2nd September 2014
quotequote all
if you obscure the windows with a frosted coating (temporary) will this be a loop hole

i have no idea what im talking about mind

Pheo

3,350 posts

204 months

Tuesday 2nd September 2014
quotequote all
How are they going to know it wasn't done after the fact, if he has a completion certificate?

Renovation

Original Poster:

1,763 posts

123 months

Tuesday 2nd September 2014
quotequote all
Thanks.

I can see it from both perspectives - I'll wait and see.

The main thing is that I don't want to lose a buyer later but I have had all the work inspected and whilst it didn't meet Planning Regs when built (as I changed it) - it does now it's complete (as I can do it under PD).



Little Lofty

3,362 posts

153 months

Tuesday 2nd September 2014
quotequote all
You dont need planning for roof lights so you'll be fine, as you could just say they were added under PD after the build was signed off.

fido

16,900 posts

257 months

Tuesday 2nd September 2014
quotequote all
Say nothing. If they ask tell them. If they want indemnity - pay for it, or not if they really want the house.