Sleeper wall and steps

Author
Discussion

Christian85

Original Poster:

869 posts

140 months

Monday 27th April 2020
quotequote all
Hi everyone. I’ve started a project in the garden of a sleeper wall and steps. Approximately 10m wide x 600m high and steps in the middle.

I’m going to lay the base layer flat on damp course membrane with 12mm studding 1 metre into the ground (through pilot holes) straight into the trench I’ve dug. I wanted to get type one scalpings but delivery looks anything up to two weeks,

My question is, will this be sufficient? I have some sand and cement knocking about but wasn’t sure if this would be counter productive with build up of moisture/damp.

Any advice and tips would be very much appreciated.

Christian

Christian85

Original Poster:

869 posts

140 months

Monday 27th April 2020
quotequote all

Lotobear

6,506 posts

130 months

Monday 27th April 2020
quotequote all
I've never built a timber retaining wall however, personally, I would omit the DPC and just lay it directly onto the ground because it will want to act as a slip plane and, further, it is unlikely to offer any meaningful resistance to moisture given your sleeper will be below ground anyway and may concievably prevent moisture from penetrating into the ground paradoxically causing the timber to become wetter than might otherwise be the case.

Secondly, I would use 22mm x 900mm road form pins and hammer them into slightly underside pilot holes, say, 900mm centres.

Some form of drainage may be advisable along the back of the timber wall.

Other views available!

pmanson

13,387 posts

255 months

Monday 27th April 2020
quotequote all
Christian85 said:
Hi everyone. I’ve started a project in the garden of a sleeper wall and steps. Approximately 10m wide x 600m high and steps in the middle.

Any advice and tips would be very much appreciated.

Christian
600m is one big step smile

jason61c

5,978 posts

176 months

Monday 27th April 2020
quotequote all

biggiles

1,744 posts

227 months

Monday 27th April 2020
quotequote all
12mm rebar pins really are quite spindly- go up to 16mm at least.

(And a long slightly-undersized masonry bit on a drill makes the ground holes pretty easy).

How will you do the end-to-end joins?

Christian85

Original Poster:

869 posts

140 months

Monday 27th April 2020
quotequote all
biggiles said:
12mm rebar pins really are quite spindly- go up to 16mm at least.

(And a long slightly-undersized masonry bit on a drill makes the ground holes pretty easy).

How will you do the end-to-end joins?
I’ll be staggering the end to end joints on the corner part where the steps start.

My friend has some of those 18mm x 1m road pins so I’m using those.

And thanks for the previous advice. Sacking off the DPM and ordered some Type 1 to collect from Wickes

4Q

3,388 posts

146 months

Monday 27th April 2020
quotequote all
I’m doing something similar as these came an hour ago

wolfracesonic

7,116 posts

129 months

Monday 27th April 2020
quotequote all
^Those look like reclaimed hardwood, I used some azobe and jarrah ones a few years ago, hard as nails; good luck!

jason61c

5,978 posts

176 months

Monday 27th April 2020
quotequote all
wolfracesonic said:
^Those look like reclaimed hardwood, I used some azobe and jarrah ones a few years ago, hard as nails; good luck!
I've used azobe. People don't believe how hard they are. There's no splinter like an azobe splinter!

Christian85

Original Poster:

869 posts

140 months

Saturday 2nd May 2020
quotequote all
Quick question, when building the steps. Do the return pieces run the whole depth of the steps? Or do you cut them the length of that tread?

For example if I’m building 6 sleeper high wall and my depth is 1200mm. do I have each piece at 1200mm, then build the steps on the inside of each piece, or do I stagger them reducing the size by 200mm (depth of step) each time?


Christian85

Original Poster:

869 posts

140 months

Saturday 2nd May 2020
quotequote all
Anyone?

Mr Pointy

11,341 posts

161 months

Saturday 2nd May 2020
quotequote all
I'm suspect from this shot of the same build that they built the return walls full length/depth & fitted the steps inside. You can see the building block foundations go the full length of the shorter return wall that forms the side of the steps:



This guy did the same as well:


Christian85

Original Poster:

869 posts

140 months

Saturday 2nd May 2020
quotequote all
Ah ok. More digging for me! I ended up like this today

Nb - I dug the middle trench to support the middle of the steps as they were going to be 2m wide if I’d of put the steps into the side walls. Will have to backfill them now

Christian85

Original Poster:

869 posts

140 months

Sunday 3rd May 2020
quotequote all
We’ve just had a thought, 200mm deep steps seems a bit shallow? I’ve dug my two trenches for the steps with the thought that my run would’ve been 200mm but now we are thinking 300mm (width of sleeper plus 100mm gravel).

With my total rise being 600mm, am I right in thinking my trenches now have to be 1800mm deep? Seeing as the steps are 100mm high x 300mm deep? Or am I going mad. It just seems a very long run of steps for not a vast height?

Mr Pointy

11,341 posts

161 months

Sunday 3rd May 2020
quotequote all
200mm does feel very shallow - even the stairs in the house are 260mm/10" going & that's not excessive (the rise is about 200mm). This was the first Google hit:
https://garden-design-courses.co.uk/outdoor-steps/

Which seems to indicate 300mm going & 200mm rise is about the limit.

Antony Moxey

8,173 posts

221 months

Sunday 3rd May 2020
quotequote all
Nothing to add other than looks a nice project OP and something I’d considered myself (our garden slopes about half a metre over half a dozen or so metres) and may revisit at some point. God luck and I look forward to seeing how it turns out.

Christian85

Original Poster:

869 posts

140 months

Tuesday 5th May 2020
quotequote all
Small update. Starting to fix them into position now (last long sleeper on the top needs cutting down to stagger corner)

Trying to do bits when I can as I’m still working nights full time, wife working from home and baby at home!

Thinking of putting some concrete into the trench on the left and at the back of the wall to make it a bit more sturdy.


Pinkie15

1,248 posts

82 months

Tuesday 5th May 2020
quotequote all
Did similar up from our patio, though not sleepers, just 'stout' wood we had lying around from our renovation/rebuild.

Step depth is 300 mm (size of paving slab)

'Treated' back of wood with some cold apply bitumen stuff had lying around after referring shed roof.

Pavings laid on blue circle 'slab layer' premix stuff.

Seem OK for the past 2.5 yrs, though must finish last step this year.


Christian85

Original Poster:

869 posts

140 months

Friday 8th May 2020
quotequote all
Wall completed. Due to changes I’ve got to order more sleepers for the steps.