Insulation on new floor - above or below concrete slab?

Insulation on new floor - above or below concrete slab?

Author
Discussion

Grandad Gaz

Original Poster:

5,099 posts

248 months

Sunday 23rd August 2015
quotequote all
Just started building an extension out back and I can't decide whether to put the celotex under the concrete slab or above. Both methods are acceptable by building control.

If I put it below the slab, that will make life easier running the pipe work around, and I just lay a 75mm screed on top. Downside doing it this way, it will mean I shall be heating up the slab as well as the rest of the house.

Help, what's the best way?

TA14

12,722 posts

260 months

Sunday 23rd August 2015
quotequote all
Insulation under the slab. No that much heat will go down, you can put a break layer in or just adjust heating times to come on earlier and finish earlier if you think that it will have much effect.

Spudler

3,985 posts

198 months

Sunday 23rd August 2015
quotequote all
Concrete, insulation, screed.

Grandad Gaz

Original Poster:

5,099 posts

248 months

Sunday 23rd August 2015
quotequote all
Thanks. Two condradicting views already. No wonder I can't decide myself!

Drumroll

3,788 posts

122 months

Sunday 23rd August 2015
quotequote all
Insulation, then concrete. but make sure you get the right density of insulation or it won't support the concrete. No need for screed if you do it that way.

Andehh

7,123 posts

208 months

Sunday 23rd August 2015
quotequote all
Makes sense sence to have the insulation as close to the floor covering as you can. No point keeping a massive slab of concrete warm is there!

I'm also for the concrete, insulation then screed. I dont see the logic of doing it any other way.

C Lee Farquar

4,078 posts

218 months

Sunday 23rd August 2015
quotequote all
We have insulation under the slab as we wanted to use the thermal mass of the concrete. IIRC a cubic metre of concrete is equivalent to 200 litres in a thermal store.

We also didn't want a layer of screed.


Busa mav

2,566 posts

156 months

Sunday 23rd August 2015
quotequote all
My stock detail has insulation above the slab.


Grandad Gaz

Original Poster:

5,099 posts

248 months

Monday 7th September 2015
quotequote all
Due to massive difference in levels between inside and outside, we have decided to go with beam and block!

Either that or we will need about 30 tons of hardcore to bring it up to the required floor level. Not to mention the amount work that goes with it. smile

ATTAK Z

11,473 posts

191 months

Monday 7th September 2015
quotequote all
Don't forget to ventilate beneath the beam and block

Grandad Gaz

Original Poster:

5,099 posts

248 months

Monday 7th September 2015
quotequote all
ATTAK Z said:
Don't forget to ventilate beneath the beam and block
No, have not forgotten smile I would have had to extend the vents from the existing suspended wooden floor anyway.

How many will I need, roughly? Every couple of metres?

Thanks

ATTAK Z

11,473 posts

191 months

Monday 7th September 2015
quotequote all
Grandad Gaz said:
ATTAK Z said:
Don't forget to ventilate beneath the beam and block
No, have not forgotten smile I would have had to extend the vents from the existing suspended wooden floor anyway.

How many will I need, roughly? Every couple of metres?

Thanks
1800 ctrs should be OK

astroarcadia

1,711 posts

202 months

Monday 7th September 2015
quotequote all
Spudler said:
Concrete, insulation, screed.
This.

astroarcadia

1,711 posts

202 months

Monday 7th September 2015
quotequote all
Spudler said:
Concrete, insulation, screed.
This.

Grandad Gaz

Original Poster:

5,099 posts

248 months

Monday 7th September 2015
quotequote all
ATTAK Z said:
Grandad Gaz said:
ATTAK Z said:
Don't forget to ventilate beneath the beam and block
No, have not forgotten smile I would have had to extend the vents from the existing suspended wooden floor anyway.

How many will I need, roughly? Every couple of metres?

Thanks
1800 ctrs should be OK
Thanks!